This page contains a Flash digital edition of a book.
[ Project focus: Olympic Stadium ]

It is a first, a unique building in the sense of what we’re trying to achieve, but I think it’s also unique in the way we’re achieving it

coordination. T Clarke has worked closely with the project’s main contractor, Team Stadium, to ensure the smooth running of the work. Bryan believes that the project exemplifies industry

best practice and demonstrates how companies can work together to their mutual advantage. ‘The companies involved in the Olympic Stadium project have created a highly productive and pleasant working atmosphere,’ he says. ‘There is no blame culture; everyone works towards a common objective and it has been very well run from top to bottom.’

Sustainability

Sustainability has been firmly on the agenda for the 2012 Games Olympic Park from the planning stage and a number of innovative ways have been developed to reduce its impact on the environment. The site features a primary substation, designed, constructed, owned and operated by EDF Energy through Lea Valley Utilities. This permanent substation will distribute electricity efficiently from the wider network of more than 100km of electrical cabling to the venues across the park. The substation is part of a wider utilities network of gas, water, electricity, telecommunications and sewage that provides a ‘backbone’ for the long-term development of the area. In October 2009, the primary substation became the first building to be completed on the Park. It now

the usual branding that you see on electrical products. Therefore, we had to ask manufacturers to remould their products without logos in order to use them. That said, all the companies we have dealt with have been happy to do this in order to have their products used.’

Lighting up time

In March 2010, the Olympic Stadium project overcame one of its toughest challenges when the first of its lighting towers was successfully lifted into place, taking the venue to its full height at 60m above the field of play. A 650-tonne crane was assembled in the middle of the stadium to lift the 28-metre-high lighting towers on to the top of the inner ring of the cable-net roof. The lighting towers will illuminate the action and are necessary for high-definition footage. They are located high above the stadium roof to ensure optimum lighting angles that will avoid dazzling spectators, photographers and competitors. They have been specially designed for this project and give the stadium its unique appearance. Bryan says: ‘The lifting of the lighting towers was a significant engineering and construction challenge, and took a huge amount of work and planning. There are 14 towers altogether and we were able to complete the necessary electrical work on them while they were still on the ground.’

Best practice

Due to the very nature of the task at hand, the Olympic Stadium development requires excellent planning and

Summer 2010 ECA Today 25 Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68