PROJECT OF THE MONTH
Left: 3.2t SWL Stahl electric wire rope hoist installation.
Left middle: For the short-term installation phase, Hoist & Winch supplied a 10t safe working load (SWL) JDN air-powered chain hoist offering 30m of lifting height.
enabled engineers to mount the hoist trolley safely to the runway beam by initially opening and then closing the trolley width around the beam section. Following installation checks and connecting the air supply, Hoist & Winch performed dynamic load testing of both the hoist and runway beam using a 10t test load over the full 30m lifting height. This process was followed by a 125% static proof load test at low level. With testing successfully complete, Hoist & Winch delivered operator handover training to the installation contractors responsible for lifting the mill’s process plant equipment into position. Phase 2 of the project involved removing the
temporary air-powered hoist and installing the permanent lifting solution: a 3.2t SWL Stahl electric wire rope hoist with 30m lifting height. Mounted on a motor-powered trolley and operating with a single rope fall, the hoist unit delivers a very high main lifting speed of 16 m/min to minimise plant downtime during maintenance lifts through the access shaft and 2.6 m/min slow lifting speed for precise load laydown at the load landing level. Hoist & Winch conducted installation, commissioning,
load testing and LOLER certification of the permanent hoist system, before providing handover training for the mill’s maintenance personnel. “Projects like this demonstrate the value of careful
planning and technical collaboration to deliver safe, efficient lifting solutions that support both the construction and long-term operation of complex industrial facilities,” says Hoist & Winch Director Andy Allen. “We subsequently secured the contract for annual hoist inspection and maintenance.”
Below: Electric wire rope hoist mounted on a motor-powered trolley and operating with a single rope fall.
Left bottom: Following installation checks and connecting the air supply, Hoist & Winch performed dynamic load testing of both the hoist and runway beam using a 10t test load over the full 30m height.
contractor constructed a platform over the lift shaft in accordance with Hoist & Winch specifications. The 10t air-powered hoist unit was raised to installation level using a temporarily mounted 2t SWL JDN air-powered chain hoist fixed to the underside of the runway beam. Once positioned beneath the beam, installation of the 10t hoist took place using a dedicated lifting arrangement comprising a pair of T-shaped lifting frames and four 1t SWL manual chain blocks. This configuration
www.hoistmagazine.com | April 2026 | 9
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76 |
Page 77 |
Page 78 |
Page 79