PROJECT OF THE MONTH
A MODERN LIFTING SOLUTION
Hoist hears from Hoist & Winch, one of the UK’s leading lifting equipment, companies on the supply and installation of a two-phase hoisting solution to support both plant installation and ongoing maintenance for a modern flour mill.
Above:
3.2t SWL Stahl electric wire rope hoist with 30m lifting height installed by Hoist & Winch at the new flour mill.
Right:
Stahl electric wire rope hoist with 30m lift height shown over lift shaft at flour mill during installation.
W
hen constructing a modern high-speed flour mill, efficient installation and long-term maintenance of plant equipment demand
a carefully planned lifting solution. For a recent project, the main contractor turned to Hoist & Winch, one of the UK’s leading lifting equipment companies. Hoist & Winch specified, supplied and installed a two-phase hoisting solution capable of supporting both the plant installation phase and ongoing maintenance activities once the facility became operational. The project required a flexible approach. During
installation, contractors required a high-capacity hoist capable of lifting heavy process equipment through a dedicated lift shaft. Upon completion of plant installation and commissioning, however, the requirement shifted to a permanent, high-speed lifting solution to support routine maintenance of the mill’s processing equipment. Following site meetings and consultations with
plant designers and project managers from the main contractor, Hoist & Winch proposed a turnkey lifting package that could meet both requirements. For the short-term installation phase, Hoist & Winch supplied a 10t safe working load (SWL) JDN air-powered chain hoist offering 30m of lifting height. Mounted in an air motor-powered trolley, the hoist was complemented by a portable diesel-powered air compressor and air hoses. Hoist & Winch also undertook installation and
8 | April 2026 |
www.hoistmagazine.com
commissioning of the hoist, along with load testing and LOLER certification of the customer’s pre-installed hoist runway beam. Operator handover training was subsequently provided for plant installation contractors.
Safe and effective lifting solutions Installing the temporary hoist system formed phase 1 of the project. To facilitate this work, the site scaffolding
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76 |
Page 77 |
Page 78 |
Page 79