CARBON AND ENERGY SAVING
will be overly complex to install; the main issue was at the design stage – in making sure the operating noise would not overly impact our (residential) neighbours. We undertook a lot of sound and acoustic surveys to measure the noise levels in various areas, and are currently demolishing an area next to the Energy Centre to create a new compound incorporating external acoustic panelling, within which the air source and water source heat pumps will go. “The scheduled completion for the
entire project will be October 2022, with commissioning continuing until around December. We will have two air source heat pumps feeding into a water-to- water pump. The philosophy of the M&E designers, Padd Energy, was that this should provide a minimum of 80% of the heat for the hospital over the whole year. There may be times when, if it gets really cold, we won’t get the required temperatures, and the pumps may be down for maintenance. We have thus also installed three new 2 MW Bosch gas boilers in the Energy Centre; the overall site heat load is about 4 MW.”
Quantifying the carbon and cost savings The bulk of the de-steaming work will be within the hospital. Michael Blades explained: “Breathe has tendered out various elements of the project – with the M&E installation work being undertaken by Imtech, its parent company.” I asked whether the team had calculated the projected carbon and cost savings. Michael Blades said he had just received the final figures, and had yet to scrutinise them. He said: “At design stage, however, we were looking to achieve an 80 per
The Northumbria Specialist Emergency Care Hospital in Cramlington.
cent reduction in carbon emissions over a 15-year period (using BEIS conversion factors). There will be very big savings in years 1 and 2, and, after that, they will fall gradually, as the National Grid’s carbon intensity reduces over time. I would probably argue that because we buy ‘green’ electricity, and purchase the REGOS (the Renewable Energy Guarantees of Origin) for this, we are using zero carbon electricity at all of our sites.” The team was also talking to other parties, such as the Duke of Northumberland, about the solar farm he may be developing on his land. He said: “As projects like that develop, we’re talking to his Estates managers to see how we can integrate and get private supplies.”
Electrical and gas contracts He continued: “Having only recently tendered for our electricity and gas contracts, we’ve stipulated that the successful bidders must allow us to look at alternative electrical supplies. So, for example, if the NSECH wanted to buy electricity from the grid, and we get the
Decontamination & Sterilisation Courses
City & Guilds assured decontamination & sterilisation training courses.
Level 2 & 4 Apprenticeships In partnership with
View our courses online:
www.avensysmedical.co.uk/training 01562 745 858
training@avensysmedical.co.uk
potential to put a private supply in from a solar farm nearby to supply most of the site’s electricity, we will still need to contract with the grid to get electricity at night time. We’re looking at the ability to get into or modify hybrid contracts as green energy supplies take off. We now also own a PPE factory in Seaton Delaval, near North Shields, as a Northumbria Healthcare FM business, and are looking at installing up to 3.5 MW of PV on the factory’s roof.”
Michael Blades has also recently
commissioned an investment grade audit of all of the Trust’s sites. He said: “Its focus is clearly on decarbonisation, and currently, under the Government’s directions, you would decarbonise by electrifying the heating. However, in parallel, the Trust has ambitions to change its entire fleet to electric vehicles by 2025, so I need to consider the impact on both the internal and external electrical infrastructure, and whether we can actually bring increased electrical supplies into some hospitals, because in locations like Alnwick there may not be sufficient capacity.”
June 2022 Health Estate Journal 55
Courtesy of Northumbria Healthcare NHS Foundation Trust
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76