3.3 West of Duddon Sands – Belfast Harbour


Overview Belfast Harbour is the first bespoke offshore wind installation and pre-assembly harbour in the UK, and is part of the Harbour’s wider plans to create a renewable energy hub. DONG and SPR leased the Harbour for the construction of the West of Duddon Sands (WoDS) offshore windfarm– a 50/50 joint venture between the two parties. This agreement resulted in a £50Minvestment by Belfast Harbour to develop a new terminal for the assembly of offshore wind turbines and provided amajor boost for the Northern Ireland construction and aggregate sectors. The 50-acre facility was used to support the construction of the WoDS offshore windfarm. SPR and DONG have supported this excellent new facility, which will benefit the future deployment of offshore wind and other sectors such as wave and tidal, in coming tomarket.


Competition


 Prior to selecting Belfast Harbour as the preferred construction harbour, SPR and DONG considered various other options and engaged with other prospective ports.


 Northern Ireland-based Farrans (Construction) Ltd was awarded the contract to deliver the new terminal by the Belfast Harbour Company.


 SPR supported Belfast Harbour Company at all stages during the harbour construction.  Constructionworks successfully executed fromthe site.


Innovation


 A deep water port with no tidal restrictions offering 24/7/365 access.  The 50-acre terminal, located on the County Down side of the Port, is the largest single investment in Belfast Harbour’s 400-year history.


 The 200,000m2 facility, is large enough to accommodate 30 football pitches.


 Up to three vessels will be able to berth simultaneously with access available around the clock helping optimise the installation plan of offshore windfarms.


Skills


 The offshore wind industry plans to install a large number of turbines within 150 miles of Belfast Harbour, thus making it well positioned geographically to facilitate the establishment of a reliable supply chain upon which to deliver this offshore wind capacity and create a sustainable local skilledworkforce.


ANNEX 3


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87