This page contains a Flash digital edition of a book.
OFFSHORE ACCOMMODATION


Whereas mistakes like these have been very expensive to fix, when it comes to personnel safety, short cuts are not an option.


POSSIBLE WAYS FORWARD There are a variety of proposed schemes being developed for safely housing and ferrying personnel to, from and within the offshore wind farms. Mother and daughter craft are proposed similar to the navy’s approach to deploying their amphibious landing craft. The Seawind concept below is an example of such an arrangement.


Through the Safety Case risk studies, the helicopter travel to and from the platforms has been shown to be the largest contributing factor to fatalities offshore so these helicopter movements are minimised by careful planning of rotas and routines of the personnel working offshore.


With the large number of farshore turbines planned, the maintenance routines cannot be supported directly by small craft operating directly from onshore due to the strict safety requirements of Maritime and Coastguard Agency (MCA). Similarly for safety reasons, routine access by helicopter is neither practical nor desirable.


Permanently moored vessels similar to a flat barge are another. The concept shown below developed by SEATEL would be designed to be moored indefinitely up to 70 miles offshore, secured using a single point mooring system and a fixed anchor spread specifically designed for each location.


Oil and Gas experience however would suggest that spread moored vessels are not the way to go for the UK waters. Spread moored Floating Production Units (FPUs) are only used in very benign waters such as offshore West Africa. For


the UKCS, weather vaning FPSOs are now deployed throughout although there are two examples of spread moored cylindrical hulled FPSOs but these are not flat barge based designs.


Flotels have been used in the oil and gas industry for many years and these are normally based on a semi-submersible hull moored to the seabed similar to a drilling rig.


Operational experience of FPSOs shows that helicopter movements are regularly hampered by the motions of the vessels in even moderate sea conditions, therefore barge based concepts would most likely not provide the operational conditions required for all year round maintenance activities.


FIXED OFFSHORE ACCOMMODATION PLATFORMS


The most obvious and well proven solution is a permanent accommodation module located within the wind farm. Separate accommodation platforms do provide all of the requirements for personnel safety and comfort.


Accommodation areas can also be incorporated into the very large HVDC platforms being proposed provided that safe barriers can be incorporated personnel protection.


A CONCEPT FOR A HVDC PLATFORM DONG Energy is experienced in oil and gas and are now well established in the offshore wind industry. For their Horns Rev II wind farm located 19 miles offshore in the Danish sector, DONG have installed a permanent Accommodation platform located alongside the Transformer Substation.


LESSONS LEARNED


Lessons can be learned from the oil and gas industry, unfortunately it is seen as an expensive industry and has been largely ignored by some sectors of the offshore wind industry leading to costly mistakes such as the grouted connections used on some of the monopile foundations.


This is the first permanent accommodation module to be installed in an offshore wind farm and sets the scene for others to follow. The maintenance crew are housed inside a standard 24 man accommodation module is designed and built to offshore oil and gas standards. The crew fly to and from onshore by helicopter allowing safe maintenance conducted 365 days a year.


www.windenergynetwork.co.uk


105


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116