This page contains a Flash digital edition of a book.
Tilling in concentrate


Raking


The 500 tonne U2 claw


Growing out freezer burns


With the two applicators spreading the fibre, two tractors and power harrows tilled in the material to the specified depth. Handraking and working around services on the pitch was also important. Spreading and mixing in of the material was carried out in two passes each. With the fibre mixed to the correct concentration the pitch was wheel rolled again and raked with a specialist rake to get final grades on the pitch. As the team retired on Wednesday evening they were two days ahead of schedule, with tolerances like a billiard table.


Thursday July 16th: Clean up


Just some finishing and tidying up was necessary before handover to the U2 concert team. Demobilisation of equipment, sweeping and cleaning of all the drains around the stadium was carried out. “Stage 2” of the project was complete and the crew left for a well earned rest.


Friday July 17th - Monday July 27th: Stage Preparations


To protect the pitch services from sinkage and settlement, a specially chosen geotextile membrane was placed over the fibre finished pitch before the plastic covering and steel flooring was placed. The U2 show was a phenomenal logistical exercise involving hundreds of trucks and personnel to build the 500 tonne ‘claw’ stage structure It took five days to build and stood out on the Dublin skyline for the eagerly anticipated shows.


Saturday July 26th: Turf Checking


The final walk and assessment of the proposed turf was carried out on the evening of Saturday 26th of July. Turf assessment techniques have been developed at STRI for the likes of Croke Park and Wembley in recent times. If the turf doesn’t pass the


Pitch prepared for All Ireland Hurling Finals just six weeks after laying


criteria, it isn’t used.


Sunday 27th and Monday 28th July: Turf Transport


Transporting turf in 90 refrigerated wagons nearly 200 miles, and then across the Irish sea over a three day period, was a logistical challenge. Too cold and the turf will suffer from freezer burn on the edges, too warm and the centre will heat in the huge 1.2m x 10m rolls. It is a really fine line between the two issues, and the damage from either extreme is a problem in a lay and play situation. There are so many functions affecting the rate of temperature drop of the turf. To credit Andy Fraser at County Turf, trials were undertaken, in the lead up to the project, to determine the perfect load, spacing and temperature to set the fridges. DSV Limited were the chosen hauliers for the project. As the last of three U2 concerts blasted out over Croke Park, ninety refrigerated wagons of turf filled a carpark on the road to Croke Park. A combination of representatives from County Turf and the STRI supervised the turf cooling and monitoring operation twenty-four hours a day, with reams of data being collected. The temperature of the wagons had to be continuously monitored and adjusted.


Tuesday July 29th: Protest


Before the U2 concert crew could start removing the stage, a local residents protest kicked off outside of the stadium at around 1.00 am. The protest was aimed at disrupting the twenty-four hour work licence granted by the local council to the concert promoters in removing the stage. All works stopped as the team sat helplessly trying to control the temperature of 15,500m2


of turf.


Finally, at 4.30pm, the residents called off the protest; and the project kicked off again, fourteen hours behind


Pitch invaision schedule.


Any time contingency was now gone and, with six games sold out for the venue the following Sunday and Monday, the pressure was on. Clive Richardson’s men were supported by Talbot Farm Landscapes and Premier Pitches in the turf laying operation. The first issue to deal with was the thawing of the turf, which takes between six to eight hours. If the thawing is left too long, the centres of the roll will heat within hours. At 10.30pm it was felt it would be beneficial to give the crew a four hour rest until 2.30 am. This also allowed the turf to thaw some more.


Wednesday July 30th: Laying continues


At 2.30am the crew of sixty returned to their positions and the job rolled on under floodlights. The U2 crew were still clearing the stage, so we had specific amounts of trucks and equipment in certain areas of the stadium which we ‘owned’ and they had theirs. At this stage there were around four hundred people working on the pitch - the U2 stage crew and the pitch crew.


Running the system worked well, with two laying machines manned by eight staff each. These were fed by eight tractors and spikes fed, in turn, by four forklifts. The choreography of operations was important; an accident would close the entire project down. As the turf was laid it was snagged by the STRI and the seams washed and rolled. As the crew continued to lay the turf, the project captured the imagination of the country, if not the local residents!


Thursday July 31st: Laying complete


As the turf was placed it became apparent it had suffered considerable ‘freezer burn’ on the edges from the extra time it had spent in the refrigerated lorries during the protest.


89


during the hurling finals


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132
Produced with Yudu - www.yudu.com