How Head Groundsman PAUL BARNETT went from keeping Scarborough fair to


Making Gretna green again ...


MY career started in my home town of Scarborough where, at the age of 16, I started working for Scarborough Town FC on a YTS placement. Two years later the Head Groundsman left the club and I was asked to maintain the pitch until they found a replacement. That never happened and I was left in charge of the stadium pitch for 13 years. I left Scarborough in 2001 to join Sunderland FC, hoping to take my career to the next level. I was looking after pitches at their Academy of Light with seven other groundstaff. However, that lasted only 18 months as Sunderland were having a bad season and were relegated from the Premiership. Unfortunately, this resulted in groundstaff being made redundant, and, sadly, I was one of them. My move to Gretna FC came in June 2003. I heard about the position from a friend, who happened to be one of the bosses at Scarborough. He rang me up to say that Gretna were looking for a groundsman and that they were interested in me. I saw this as a great opportunity and was happy to join them two weeks later.


Due to the timing of my appointment, I only had four weeks to prepare the playing surface for the first friendly. The pitch was being maintained by the manager before I became Head Groundsman. The playing surface was still young and needed some attention quickly to have a strong sward for the start of the season.


I am pleased to say that the pitch has been playing its part over the last 3 years as Gretna have progressed through the divisions. They are now ready for


the First Division and then, hopefully, the Premier League. We are in the process of redeveloping


the ground to make way for two new stands to meet SPL standards, which require a 6000 seater stadium. This meant knocking down an old stand and adding 20 metres to the width of the existing pitch. This will allow us to move the pitch over during the season, still retaining the same pitch dimensions, and for a new stand to be constructed on the opposite side coming 20 metres on to the existing pitch. All this work was due to be completed by 5th August, so we had to move quickly to organise contractors for a start date as we only received permission in mid May.


Diary of works:


Contractors removed old stand and terracing down to a sub level of 350mm.


Hellens Sports started preparation works to bring area to right height of 100mm off the surface.


Par 4 Irrigation started putting in extra irrigation pipes and pop up sprinklers around new area.


Drainage works lateral pipes at 5 metres apart with main drain fix on to main pitch drainage.


Preparation ready for 35mm thickness turf to be laid.


All works were carried out within three weeks. The pitch was laid and fertilised with a 12.0.9 + 2%Fe two days later. We watered the new turf and our first cut was five days later at 32mm, the same as we cut the main pitch.


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99