Concrete firm delivers for multi- million-pound distribution centre project


Owen Batham, sales and marketing director at Elite Precast Concrete Limited, says the company has supplied over a thousand of its Legato interlocking blocks for the construction of a huge retaining wall at a new distribution centre in Dunstable.


W


est Midlands-based Elite Precast Concrete was called upon by construction


       blocks to build a retaining wall as part of the development of the Prologis distribution centre 


The blocks were used to create a 220m long and 5m high retaining wall at the new facility, providing a quicker, better value      to the standard gabion baskets that had       contractor, was working to a tight timeframe and contracted specialists PNR Construction to prepare the foundations and install blocks. The project involved the very highest level of team-working between all the companies and


the incredible result was that in just 10 working days over 1,000 Legato blocks were delivered and installed.


The 310,000 sq ft distribution centre is


strategically located close to the M1 and is part of a development to provide more distribution centres in the south east, which has a severe shortage.


We were delighted to support Winvic and PNR  to aid the project’s fast turnaround time. Our blocks are all stock items ensuring an instant response and a quick and hassle-free build.


The Legato blocks are ideal for constructing retaining walls and incorporate their own cast-


in lifting pins which mean they are extremely quick and very safe to install.


      construction project was particularly time- sensitive and the Legato blocks were the perfect option, not least because they could be delivered and installed within a very short  site excavation was only accessible for a limited period, so the easy installation of the blocks was a huge safety advantage. The streamlined collaboration between Elite Precast Concrete and PNR Construction, who installed the 


W: www.eliteprecast.co.uk FOR MORE INFORMATION


Arriva TrainCare on track with advanced fuelling technology


Cameron Forecourt sales and marketing director Martyn Gent describes the advantages of new fuelling equipment. T


he latest advanced fuel management systems from UK commercial


fuelling


specialist Cameron Forecourt is now being used to monitor the fuelling of rail vehicles at three sites operated by Arriva TrainCare.


Key depots at Crewe, Cambridge and Tyne Yard can now be monitored in ‘real time’ round-the- clock throughout the year using Jigsaw Eclipse fuel management systems and high accuracy  installed and commissioned as a turnkey package by Cameron Forecourt.


Rail vehicles calling at the three depots for fuel each have a unique number, which is entered into the system via keypads on the Jigsaw Eclipse fuel island terminals. Once successfully       


78 | rail technology magazine Dec/Jan 15


authorised fueller to replenish the fuel tanks with gas oil via the pumps.


Information from each fuelling is then fed to the Cameron Forecourt’s twin central servers in Manchester, which can be accessed by authorised managers from any PC, laptop or smartphone using any internet browser.


The largest facility is at Crewe, where the installation comprises 11 Jigsaw Eclipse fuel island terminals drawing fuel supplies from four main fuel tanks, each of which is constantly            Cambridge and Tyne Yard feature the same system but with a single fuel island terminal.


    


information on stock levels, remaining tank capacity and ullage, allowing managers to maintain safe working levels and to arrange replenishment, which is carried out regularly via road tanker deliveries.


Fuel drawings monitored by the Jigsaw Eclipse system can then be reconciled against fuelling from the tanks. Fuelling can take place at any time of day or night. The integrated package allows Arriva TrainCare to keep a constant check on fuel movements, stock levels, and consumption, providing complete and accurate wetstock reconciliation around the clock.


FOR MORE INFORMATION


T: 01226 742441 E: info@cameron-forecourt.co.uk W: www.cameron-forecourt.co.uk


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108