This page contains a Flash digital edition of a book.
WORKSHOPS, DEPOTS & LIFTING EQUIPMENT


Piling work underway at Crossrail’s eco-friendly Old Oak Common depot


Work is well underway to design and construct Crossrail’s new eight-track depot for its Bombardier-built train fl eet at Old Oak Common (OOC), with piling starting as RTM went to press. Senior project manager James Mendis spoke to David Stevenson.


B


ombardier Transportation UK Ltd awarded Taylor Woodrow the £142m contract to construct the new Old Oak Common (OOC) Crossrail depot, which will house 33 trains, in June 2014. The depot will be operational by May 2018.


Iain Gascoine, Bombardier’s project director              Construction UK, took possession of the former GWR locomotive and carriage servicing depot at OOC – situated at Acton in West London.


       establishment for the duration of the four- year project, completed the demolition of the Pullman-sheds, and have cleared buried services underground.


James Mendis, senior project manager at Taylor Woodrow (the civil engineering division  project, added that the team is now embarking on detailed designs for the facility and piling work at the site starting. “The week beginning 12 January we start piling,” said Mendis, “and there are approximately 250 piles to go into the ground for the building. We aim to have this complete by May.”


The sequence of construction, he added, will be piling, followed by pile caps and drainage, followed by steel frame erection, cladding          construction of the pits. In parallel with these works the drainage to the main site will be installed along with the connection to the main line and stabling sidings and the associated signalling and OLE works for the depot.


Eco-depot


       it had signed a contract with Bombardier for the delivery of rolling stock and the new depot for Crossrail. The 65 new Class 345 nine-car EMUs will be manufactured and assembled at  to be delivered in May 2017.


But as part of the 32-year maintenance contract, which includes an option to purchase 18 additional trains, there was an obligation to 


To achieve this, energy at the OOC depot will be generated and stored using a hybrid   Ground source heat pumps will control heating and cooling, originating from a combined heat 


Gascoine told us: “This was something we worked with Crossrail on, and we had an obligation to get a BREEAM rating of ‘good’.        using the new technology, we aim to achieve ratings of ‘very good’ to ‘excellent’.


“We will also be able to reduce our power requirements by one megawatt per year as a  the 32-year period of maintaining the trains.


 the solar power. That’s also coupled with              requirement to achieve a 20% reduction in power requirements in real-terms – we are now looking at achieving 30%.”


With regards to the ground source heat pumps, Mendis noted that as part of the construction the piles are to have geothermal loops installed.


“In addition to that we have got approximately 50 boreholes, which are 150m deep and about 150mm in diameter, going into the ground. They have thermal loops in them as well,” he said. “This will be used to heat and cool the building.”


Demolition There have


is not a rail site at the moment, with no live track in and out, work has progressed without problems.


“The site won’t become a live railway until 2017-18 when we start to electrify and power- up the overhead lines and get the test trains running,” said Gascoine.


       We have made good progress on the demolition and that’s mainly where we could have hit problems, but so far we haven’t.”


Mendis added that because Taylor Woodrow and Bombardier are co-located it has made it easier to rectify any on-site issues if and when they have occurred.


Depot’s long-term legacy


The construction of the maintenance depot at OOC is expected to support 244 jobs, plus 16 apprenticeships. And when fully operational the depot will support 80 jobs to maintain the 


     Taylor Woodrow and its supply chain partners would take on 13 apprentices. Bombardier has 


“We have an obligation under the contract with Crossrail to apply responsible procurement, which is recruiting from the local environment,” explained Gascoine. “That has a big impact on Bombardier, more than Taylor Woodrow, because we have to run the maintenance depot, so most of our recruitment will be done locally.


been few challenges for the


construction teams so far, Gascoine said, and the land – the former OOC diesel depot – is favourable. Because the development area


 as the site being environmentally-friendly, this will enhance the chances of long-term employment and of apprentices over the next 32 years.”


James Mendis


opinion@railtechnologymagazine.com TELL US WHAT YOU THINK


rail technology magazine Dec/Jan 15 | 69


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108