Work to pick the contractors on the Crossrail project is steaming ahead, reports Kate Ashley. T


he competition for the con- tract to construct the final


tunnel portal at Victoria Dock as part of the Crossrail project is un- derway, with the work estimated to be worth £50m.


Crossrail published the contract at the end of July and the deadline for expressing interest was August 24. It is expected that the contract will be awarded by spring 2012 and work will commence in the autumn.


Victoria Dock portal is one of five new tunnel portals to be built at part of the Crossrail project. The other tunnels will be at Pudding Mill Lane, North Woolwich, Royal Oak and Plumstead.


Work first started at Royal Oak portal, and is due to be completed in early 2012. Then the first Cross- rail tunnel boring machine will


© Herrenknecht AG


curement process for the remain- ing Crossrail tunnel portal is now underway. The contract for Vic- toria Dock Portal will be awarded next year.


set out on its journey from Royal Oak towards Farringdon in spring 2012.


The North Woolwich and Plum- stead portals are included as part of main works for the C310 Thames Tunnel contract. Ena- bling and mobilisation works are currently underway at Plumstead with utility diversion and ground clearance works ongoing at North Woolwich.


Enabling works for Pudding Mill


Lane Portal started over a year ago and are on schedule to be complet- ed at the end of 2011. Main con- struction for Pudding Mill Lane Portal is now underway.


Due to the close proximity of the Crossrail worksite to the Olympic Park, work on Pudding Mill Lane Portal will be suspended during the London 2012 Olympic and Paralympics Games.


Andy Mitchell, Crossrail Pro- gramme Director, said: “The pro-


“Construction of Royal Oak Portal is advanced and is due to com- plete in early 2012 ahead of the first tunnel boring machine be- ing launched from Royal Oak in spring 2012.


“Main construction at Pudding Mill Lane Portal is now underway with advance and enabling works progressing at the North Wool- wich and Plumstead portal sites.”


Companies who have registered their interest for the Victoria Dock contract will be announced in the near future.


FOR MORE INFORMATION Visit www.crossrail.co.uk


rail technology magazine Aug/Sep 11 | 37


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92