This page contains a Flash digital edition of a book.
CIVIL ENGINEERING & CONSTRUCTION


Martin Kennedy, director of quantity surveyors Kennedy Solutions, explains what can go wrong in construction contracts.


C


ommercial management of construc- tion projects – whether building, civil engineering, rail or petro-chemical – should be a straightforward occupation.


When you look at the structure that makes up typical construction contract documen- tation - the terms and conditions of con- tract, the drawings, the specifi cation and the pricing document – all of the bases ap- pear to be covered.


Armed with such an array of tools what could go wrong? Well, several things actually!


On the contractors’ side:


Late receipt of information; late approval of design; late approval of the programme; incorrect rejection of design; scope creep; delayed access to site; cancelled posses- sion; etc…


On the employers’ side:


Slow mobilisation; insuffi cient design staff; late submission of designs; poor quality of design; late procurement of material; inad- equate site management; lack of co-ordi- nation; insuffi cient detail on programme; delay to programme; etc…


In modern contracts, even more unknowns are expected to have been considered and included in the Contract Sum – as part of a risk register.


All of the above events occur on a regular 32 | rail technology magazine Aug/Sep 11


basis and at fi rst glance there is a mecha- nism in the contract to deal with all of these events.


But unless either party has fully document- ed the events at the time – and in accord- ance with the contract – the injured party will have put itself at risk of being unable to recover full entitlement in respect of time and cost.


Too often, it is only when things begin to go wrong that the parties start to look hard at the contract.


Ideally before the start of the contract, it is important that both parties understand their respective obligations within the con- tract and work to an accepted programme.


This is where effective commercial man- agement is required. Good early advice and the setting up of appropriate commercial systems can in many cases save substantial sums of money, not to mention the stresses involved in dealing with potential contract disputes.


The above is not to say that all contracts are perfect. The contract only refl ects the pro- cess the parties have agreed to – for better or worse. Certainly, there is occasion when the documentation is not of suffi cient accu- racy and is open to differing interpretation. Such matters can be dealt with by a third party if necessary.


Our experiences have shown that parties to the contract do generally understand their


respective duties and obligations. How- ever, on occasion a party will avoid taking an action in accordance with the contract when it thinks it may “upset” the other side.


Good relationships are put ahead of essen- tial contract administration of the contract.


This will usually result in much wringing of hands and gnashing of teeth when such relationships are found to be built on shift- ing sand.


In summary, when you enter into a contract, ensure that you adhere to its provisions.


Such adherence does not mean that every- thing will run smoothly, but it will provide clarity as to the method of resolution and the best chance of a recovery in respect of time and/or cost.


Failure to do so will weaken your negotiat- ing position.


Kennedy Solutions has vast experience in commercial management, claims avoid- ance and claims management in all con- struction sectors. Kennedy Solutions has Link-Up accreditation for work on Network Rail and London Underground projects.


FOR MORE INFORMATION


If you have current unresolved commercial issues, email info@kennedy-solutions.com or visit www.kennedy-solutions.com


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92