of Le Havre for the Sarens technical team to have all the equipment necessary to carry out the entire operation. To ensure that the marine spread used
for the installation offshore of the GBSs does not suffer downtime Sarens is using a 24-hour loading process for the barges. Three foundation bases are loaded on each barge, in a continuous operation of maximum 38 hours per barge. This process must be repeated 24 times, which will require the participation of a large number of highly specialised f