search.noResults

search.searching

saml.title
dataCollection.invalidEmail
note.createNoteMessage

search.noResults

search.searching

orderForm.title

orderForm.productCode
orderForm.description
orderForm.quantity
orderForm.itemPrice
orderForm.price
orderForm.totalPrice
orderForm.deliveryDetails.billingAddress
orderForm.deliveryDetails.deliveryAddress
orderForm.noItems
LUIS VALENZUELA P, RAMON VERDUGO A, JOSE CAMPANA Z & CARMEN G OPAZO A


and piezometric level records, the deposition slope was changed to 1:3.5 (V:H). A final slope of 1:3 (V:H) is considered for the closing stage[28].


Although this dam had not been built at the time of the Valparaíso earthquake in 1985, there were already accelerometers installed in the rock at the dam site and the recordings of this strong and relatively close earthquake were considered later in the dam’s dynamic stability analysis. Two large earthquakes have been registered during the operation of the


TSF: the 27th February 2010 earthquake, Mw = 8.8, and the 16th September 2015 earthquake, Mw = 8.4. In both seismic events, no significant damage or deformation was observed. The instrument, located in hard soil and associated with the main dam, recorded the data shown in Table 6[42].


Table 6. Recordings of large earthquakes in Las Tórtolas main dam(1)


The Quillayes Tailings Storage Facility (TSF) is of special interest due to a series of conditions that translated into the implementation of severe design, construction and operating restrictions. The Los Pelambres mine project is located 300km north of Santiago, with the TSF located near the other mining facilities. The site is in the foot hills of the Andes Mountains, at an average elevation of 1400masl, approximately 85km from the Pacific Ocean. Operation of the TSF began with a planned maximum capacity of 257 million tons of dry tailings, but a final capacity of 360 million tons was achieved with the final height of 198m∗ of the tailings sand dam[43].


The main dam is a tailings sand dam constructed from the hydraulic deposition of sands obtained from cycloning of the produced tailings, originally designed to have a maximum height of 175m after seven years of operation. The starter dam was a 70m-high compacted


228 DAM ENGINEERING


Vol XXXI Issue 3


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95