This page contains a Flash digital edition of a book.
TRACK TECHNOLOGY


Ladbroke Grove points repair


Karl Gilmore of AmeyColas explains more about a seemingly intractable points maintenance problem and how it was eventually solved – requiring some new thinking.


A


troublesome set of points in west London whose height needed reducing – but for


which access using traditional methods was virtually impossible – were finally tackled using a new solution.


Karl Gilmore, the project manager at AmeyColas responsible for dealing with the problem, said that various traditional approaches were explored but rejected in seeking to reduce the height of points 8057 at Ladbroke Grove by 125mm.


Access with road/rail vehicles was not an option, and the lengthy possession times that would be needed to complete the task using traditional methods on one of the country’s busiest main lines meant the set of points and its crossover were inoperable for about 18 months.


This necessitated re-writing of train paths, to the annoyance of the train operating companies. Gilmore had heard about a new way of excavating track ballast, and watched the videos of the RailVac product, before speaking to Railcare’s Steve Mugglestone to arrange a live demonstration at the Kirton Lane level crossing site in Doncaster earlier this year.


Gilmore said: “The weather was simply appalling. There was a foot of snow, freezing temperatures, in fact everything that would normally mean cancellation.


“Simply getting there proved a challenge of Arctic proportions!


“However, despite all that the Bridgeway Railcare team and the RailVac were ready and waiting to go into action as scheduled.


“I was really surprised by the Railcare team’s ‘can do’ and very positive attitude – it’s inspiring, it filled me with confidence and their enthusiasm is infectious.”


He praised the “extraordinarily high” reliability record of the equipment, and the fact that the team provides its own staff for jacking and packing, and since they were trained fitters with spares, they could deal there and then with issues like machine stoppages.


Gilmore said: “The only barrier I could envisage was the cost compared to traditional techniques, but its sheer speed makes the per hour cost significantly cheaper overall, by comparison to bringing a lot of other kinds of equipment by road but needing twice or three times the possession time, plus all the labour involved, etc.


36 | rail technology magazine Dec/Jan 13


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92