East Anglia THREE Offshore Windfarm


The table below sets out the key project design characteristics associated with the proposed East Anglia THREE Offshore Windfarm.


PROJECT CHARACTERISTIC Size


Windfarm capacity


Estimated no. of houses (equivalent)* Distance from Lowestoft Number of wind turbines


Minimum spacing between wind turbines Size of turbines


Maximum height of wind turbine Landfall of export cable Grid connection point


Number of convertor stations ONE 306km2


1,200 megawatts 821,273 45km


Up to 325 675 metres


3-8 megawatts 200 metres


To the south of Bawdsey


Bramford 1


THREE 305km2


1,200 megawatts 821,273 69km


100-172 675 metres


7-12 megawatts 247 metres


To the south of Bawdsey


Bramford 1


* Calculated using a 33.04% capacity factor (the UK average for offshore wind as supplied by DECC Digest of United Kingdom Energy Statistics) and an annual household consumption of 4,229 kW hours


Project timelines We intend to submit an application for consent for East Anglia THREE in November 2014. As with any project, these dates are subject to amendment throughout the development process.


Preliminary


Scoping request Q4 2012


Environmental Informaon


Report published Q2 2014


Applicaon submied Q4 2014


Planning decision 2016


12 34 56 7


Environmental Surveys commence and idenficaon of individual projects Q1 2010


East Anglia THREE timeline


Publicaon of The Statement of Community Consultaon (SoCC) Q3 2013


Construcon commence 2019/2020