Technical


Shelton’s gravel bander in operation


Installing secondary drainage to rugby pitch


the drain will only accept water from the area directly above it and slightly to the side. Pipe drainage systems are only effective when there is a zone of ‘free-water’ at the depth that they are installed. In this situation, the drains will ‘pull’ water that is above and to the side of the drain line due to the hydraulic head of water created above the drain.


Planning a drainage system means calling


in the experts. Sportsturf consultant, Gordon Jaaback, says; “A detailed professional investigation of the project beforehand should identify most of the problems. A comprehensive work plan and specification prepared by a consultant gives the contractor a clear idea of the scope of the work that is likely to be involved.” “Technical decisions reached early can


prevent unnecessary costs. Nothing is more costly to a contract than repeating an item of work that should have been done correctly the first time.”


Sand slit drainage systems Gordon Jaaback “ 120 I PC APRIL/MAY 2014


These systems are effective at increasing the drainage rate of a site as they effectively


bypass the soil and the sub-soil by providing a connection between the surface and the gravel over the pipe drain line. Sand slit drainage systems can often


become sealed at the surface after play. Heavy sand topdressing will reduce this problem, but the potential for capping the coarse grit-sand in a slit with the finer sand used for topdressing is sometimes a problem encountered by consultants. Good contractors are familiar with the properties of all types of sand.


Perched water table constructions


The majority of higher profile pitches and golf greens are constructed using this principle. The construction profile usually consists of a medium sand dominated rootzone over a gravel layer with drains below. A blinding layer of grit sand is often included between the rootzone and the gravel.


The profile always consists of finer


materials overlying coarser materials. Water will only move downwards through


the rootzone when the gravitational pull on the water exceeds the adhesive and cohesive


A detailed professional investigation of the project beforehand should identify most of the problems


Installing primary drainage to golf course fairway


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152  |  Page 153  |  Page 154  |  Page 155  |  Page 156