This page contains a Flash digital edition of a book.
safety alerts


Near-miss with live electrical cable


Compiled using information provided by the Marine Safety Forum, www.marinesafetyforum.org


SERIOUS NEAR-MISS WITH LIVE ELECTRICAL CABLE


A recent incident on a vessel highlighted the importance of a close interface between contractors working on board and crew. During the demobilisation of contractor equipment, the equipment had to be ‘Locked Out’ and ‘Tagged Out’ (LOTO) to ensure that a ‘zero energy state’ had been achieved before work commenced. The contractor visited the ECR and, with vessel crew, locked and tagged out the system and started work. The power was verified to be locked out at the equipment and isolated at the breaker in the deck distribution box. Work commenced. During work the lock-out key was passed to another member of the contractor team who proceeded to the ECR to remove the LOTO and re-energised the system. The de-energised cable from the equipment had been disconnected and placed on the chassis but when the LOTO was removed from the ECR switchboard the cable became live with 440 volts and 100 amps passing through it.


Assessing that the cable remained de-energised, another


contractor employee


had to move it to access the work. In doing so, his hand was very close to the live cable ends. The cable ends touched the chassis and arced, causing a loud bang. An immediate safety stand-down was enforced by the contractor. Fortunately, no one was injured as a result of this incident.


A number of causes were identified after the event. These included: • no vessel involvement in job content or planning and no contractor project manager designated for work • no job safety analysis developed as per bridging document requirements • a permit required but was not raised for isolation • no contractor work permit was completed for the LOTO as required by the established bridging document • a multi LOTO was not used and a single key


88 I Offshore Support Journal I June 2012


passed to the team member • a voltage discrepancy for breaker isolation resulted in the contractor’s inability to confirm zero voltage • the deck cabinet was exposed to the elements and not easily accessible. It was not fit for purpose • electrical drawing was not a controlled document. No drawn by, checked by or approved by and no class/type approval • no recognition of labelling on adjacent breakers • the superintendent did not follow up on concern with isolation of correct breaker • the superintendent had a dual role, supervising one ROV crew and overseeing all ROV personnel. As a result of the incident, 18 corrective actions have been identified and are in the process of being implemented. The incident could have resulted in a fatality. It should not have happened and could have been prevented if all of the proven processes already in place had been used.


FINGERS LACERATED BY ROTATING MACHINERY


During the forenoon watch the chief engineer noticed that one of the clamps for the cooling pipes on main start air compressor number 1 had fallen off, presumably because of vibration, and was lying underneath the air compressor. He had a conversation with the third engineer, who was asked to remove the clamp from under the compressor and fit time permitted.


it during his watch if


The task was to offer up the cooling pipe lower clamp from the underside of the compressor and to secure it in position with a single bolt/nut. A ring spanner was to be used to hold the upper bolt and a ratchet wrench to tighten the nut on the lower clamp.


The third engineer positioned himself on his


left side on the engineroom plates to conduct the task. Using his right hand he positioned the ring end of the spanner in from the right side of the cooling pipes onto the bolt head. From the underside he offered up the clamp and put the nut onto the bolt, then proceeded to tighten using the ratchet wrench.


The third engineer continued to tighten the nut with a ratchet wrench and the compressor automatically started up. This caused the fan blade to rotate at high speed, making contact


with his left hand, knocking it downward. This caused lacerations of the finger which resulted in the vessel being re-routed back to port. The incident could have resulted in the loss of fingers or a hand.


Among the critical factors that contributed to the incident were a failure to assess and control hazards, and incorrect positioning of body parts. A contributing factor was that the personnel in question were not wearing any form of hand protection (which might have reduced the extent of the injury).


The individual was fully aware that he was taking a risk, but decided to do the job, resulting in a shortcut being taken.


Isolation of the


compressor was not conducted as he deemed the task to be a ‘two-minute job.’ Instead of performing the work in accordance with company procedures he failed to carry out a risk assessment and failed to put appropriate controls in place to minimise the risk. During the investigation interview the injured party stated that the compressor had just completed a cycle and, therefore, he did not believe it would start again. He also said he had conducted “a mental risk assessment”.


GRINDER


An AB seaman on a vessel operating close to a platform suffered an injury to his right leg – just above the knee – resulting in a 5cm cut. While waiting instructions from the platform, he had been ordered to brush the upper stern part of the crash-bar (starboard side) with an electric grinding machine. Whilst doing so, on top of a ladder, he lost his balance and the tool fell to the deck, injuring him in the process. He was given medical assistance by crew members and the doctor on the platform recommended sending him to hospital ashore.


The grinder had no emergency stop system and continued rotating once dropped. The seaman should not have used a ladder to carry out the work, and the ladder was not secured. The deck was reported to be slippery at the time. The status of the crash-bar did not justify the urgent maintenance activity. There was no evidence of planning the activity/toolbox talk, or evidence of a permit to work. The two seafarers working on deck (the AB and bosun) were working independently (not as per the permit to work requirements). OSJ


www.osjonline.com


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152  |  Page 153  |  Page 154  |  Page 155  |  Page 156  |  Page 157  |  Page 158  |  Page 159  |  Page 160  |  Page 161  |  Page 162  |  Page 163  |  Page 164  |  Page 165  |  Page 166  |  Page 167  |  Page 168  |  Page 169  |  Page 170  |  Page 171  |  Page 172  |  Page 173  |  Page 174  |  Page 175  |  Page 176  |  Page 177  |  Page 178  |  Page 179  |  Page 180  |  Page 181  |  Page 182  |  Page 183  |  Page 184  |  Page 185  |  Page 186  |  Page 187  |  Page 188  |  Page 189  |  Page 190  |  Page 191  |  Page 192  |  Page 193  |  Page 194  |  Page 195  |  Page 196  |  Page 197  |  Page 198  |  Page 199  |  Page 200