Fallpipe ship completed by thriving builder


Singaporean shipyard Keppel Singmarine, part of Keppel Offshore & Marine, is on schedule to deliver a new-generation fallpipe vessel to Dutch company Boskalis. The group has also secured several other orders recently


ue to enter service shortly, Rockpiper, Boskalis’ new fallpipe ship can carry 24,000 tonnes of rock and is equipped to carry out precise rock dumping work in water depths of more than 1,000m. Equipped with a dynamic positioning system, the 159m, double- hull vessel can be navigated very precisely whilst lowering rocks through a fallpipe at a controlled rate in order to provide protection to cables and offshore pipelines.


D Rockpiper is one of a number of projects that the yard has undertaken for Boskalis


A naming ceremony for Rockpiper was held on 28 January 2012 at Keppel Singmarine. The yard’s relationship with Boskalis dates back many years, with successful deliveries of various newbuilds, shiprepair projects, the ‘jumboisation’ of a trailing suction hopper dredger and a number of upgrading projects. At the time that the new fallpipe ship was named, Keppel was also upgrading the dredger Taurus II for Boskalis. The design for the new fallpipe ship is a


completely new one. It has a rock dumping capacity of approximately 2,000 tonnes/hour and can dump rock to a depth of 1,500m, if required. The fallpipe itself has an inner diameter of 700mm. The sophisticated new vessel has diesel-electric propulsion comprising three main diesel generator sets and an auxiliary diesel generator set. The accommodation is on the fore ship and is arranged for a complement of 60. The rock dumping equipment that feeds the fallpipe is arranged in the mid-ship area along with a moonpool. The fallpipe is innovative too, having its own integrated survey


remotely operated vehicle (ROV). Yards in the Keppel Offshore & Marine group have an established track record of building specialised ships with a wide range of designs and functions. In March, Keppel FELS (KFELS) entered into a letter of intent with a repeat customer, Floatel International Ltd, to build a new-generation harsh environment accommodation semi-submersible worth US$315 million. Due for delivery in July 2014, this will be Floatel’s fourth accommodation semi-submersible from Keppel, following the delivery of Floatel Superior and Floatel Reliance in 2010 and the order of Floatel Victory in 2011. The new semi-submersible will be based on the Floatel Superior design, a DSS 20NS design developed by GustoMSC and Keppel FELS’ Deepwater Technology Group. Equipped with DP3, it will meet the most stringent rules and regulations for worldwide


operations


including the Norwegian sector of the North Sea. When completed, the new unit will be able to accommodate 440 persons in single-bed


cabins with ample recreation areas as well as offices. Well equipped with a host of facilities, the unit is also suitable for construction support during new construction, maintenance activities or for decommissioning projects. Other


recent orders have seen Keppel


Shipyard secure floating production, storage and offloading (FPSO) upgrade projects from long-term partners SBM Offshore and Bumi Armada Berhad (Bumi Armada). The combined contract value of the two projects is S$170 million (US$136 million).


The first project is from SBM Offshore, to refurbish and upgrade the FPSO Xikomba. Work on the unit is expected to be complete by the third quarter of 2013. The second project will see Keppel Shipyard modify and upgrade Bumi Armada’s FPSO Armada Claire. This


includes


refurbishment and life extension works as well as installation and integration of topside modules. Work is expected to commence in the third quarter of 2012 and be completed in the fourth quarter of 2013. OSJ


Technip awarded pipeline installation contract in China Technip has been awarded a pipeline


installation contract by Offshore Oil Engineering Co Ltd for the Liwan 3-1 shallow-water project. The project is in the Pearl River Mouth Basin, China Sea, at approximately 300km south of Hong Kong, China.


With a total length of 260km, the pipeline will 36 I Offshore Support Journal I June 2012


link the Liwan gas platform to China National Offshore Oil Corporation's (CNOOC) Gaolan gas plant.


Technip’s scope covers the shallow-water portion of the development project. It includes the installation of 160km of 30in export oil/gas two- phase pipeline from the Liwan gas platform to a


water depth of approximately 70m.


Technip’s operating centre in Singapore, in liaison with the project engineering office in Shekou, China, will execute the contract, which is scheduled to be completed by the end of 2012. Offshore installation will be carried out by Global 1201.


www.osjonline.com


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152  |  Page 153  |  Page 154  |  Page 155  |  Page 156  |  Page 157  |  Page 158  |  Page 159  |  Page 160  |  Page 161  |  Page 162  |  Page 163  |  Page 164  |  Page 165  |  Page 166  |  Page 167  |  Page 168  |  Page 169  |  Page 170  |  Page 171  |  Page 172  |  Page 173  |  Page 174  |  Page 175  |  Page 176  |  Page 177  |  Page 178  |  Page 179  |  Page 180  |  Page 181  |  Page 182  |  Page 183  |  Page 184  |  Page 185  |  Page 186  |  Page 187  |  Page 188  |  Page 189  |  Page 190  |  Page 191  |  Page 192  |  Page 193  |  Page 194  |  Page 195  |  Page 196  |  Page 197  |  Page 198  |  Page 199  |  Page 200