Production • Processing • Handling


Inconel 718, which also helps guarantee that rigorous safety specifications are met. Carrying out a full engineering review of components such as adapter plates, bolts, couplings and stem materials and procuring these items from the actuator manufacturer also ensures that the package will fit together correctly. Crucially, it can also prevent mistakes


and ‘grey areas’ arising in the supply chain process when, for instance, the components have been sourced from different third-party suppliers – a common source of headaches and delays. A full review of the control system should also be conducted – again using engineering disciplines to ensure the right components are assembled.


On-track and on-time Once the engineering issues are resolved, the project moves on to the manufacturing phase. Here, communication is key, which is why the supplier will ensure the valve and actuator manufacturers are clear on the specifications at an early stage and that all the necessary components fit together first time. In addition, scheduling and submitting inspection and test plans ensures the manufacturer knows that formal inspection processes will take place and will maintain discipline and punctuality throughout the order. A pre-inspection meeting between all


parties again ensures the necessary tests and documentation are provided and that all expectations are met without disruption during the testing phase.


Typically, however, these VACs often do not have the depth of facilities found at manufacturers’ facilities. For this reason, HSP believes a


more effective approach for suppliers is to leverage strong relationships with manufacturers and schedule the testing phase at the manufacturer’s premises, ensuring access to a wider-range of valve types, lifting equipment and pressure and temperature testing capabilities. Tis also removes the potential requirement for a re-test, in turn ensuring the actuation package is certified and passed for delivery in the fastest possible time.


Fig. 2. Documentation and certification is fundamental. Often, global distributors use Valve


Actuation Centres (VAC) to test the valve and actuator in a workshop environment.


72 www.engineerlive.com


Issue of documentation Documentation and certification is a fundamental part of the procurement process as it enables oil and gas assets in particular to trace components. Without the necessary documentation, the order cannot be finalised. A further priority task for the supplier is to submit a general arrangement drawing that shows the valve and actuator together. When buying directly from a manufacturer or VAC these drawings will typically not be provided quickly and yet they are often crucial for clients as they lay out facilities. For this reason, unlike many other suppliers, HSP guarantees the drawings are delivered within four to six weeks. Tis added service is extremely valuable for the client, as it allows engineering work to continue and ensures the programme stays on schedule. No matter how many valve and actuator manufacturers are involved in the order, the documentation for actuation packages needs to be presented in a consistent format and in accordance with the client’s requirements. It should also include pre-approved inspection materials such as ATEX and SIL electrical design certification. To help ensure projects stay


on track, HSP ensures final delivery of dossiers within four weeks of the actuation package arriving at the plant or asset. ●


Be responsive to change


In addition to strong engineering acumen and supply chain relationships, the most important quality a good actuation supplier needs to have is responsiveness.


Specifically, this means orders should be adapted in accordance with engineering comments and changes need to be adhered to without issue – however late in the process. Notices for inspection should be on time and the inspector should always have access to the right people and the appropriate documentation.


Gordon McNair is engineering manager with HSP Valves, Newbury, Berkshire, UK. www.hsp.co.uk


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100