£81m reliability upgrade to WCML at Watford


Network Rail has chosen five long blockades rather than 54 weekend closures to improve the West Coast Main Line around Watford. Kate Ashley explains.


N


etwork Rail has announced improvements to the West Coast Main Line around


Watford to improve punctuality and reliability, including works not done under the 10-year, £9bn West Coast Route Modernisation.


The £81m scheme is to take place over five closures throughout 2014 to avoid closing the line completely over 54 weekends.


Work will include renewing three junctions around the station to improve the track layout and increase reliability, as well as renewal of nine miles of track, upgraded overhead line equipment, 12 miles of signalling renewed and an upgrade to the signalling power supply system.


Dyan Crowther, Network Rail route managing director, said: “This scheme represents significant investment in the southern end of the West Coast Main Line to improve punctuality and make the railway more reliable.


“This line has seen tremendous growth in traffic


and passengers over the last five years with the section at Watford being one of the most intensively used, high-speed sections of track in the UK. This work is absolutely essential to maintain the punctuality that passengers and our freight customers rightly expect.


“There is never a good time to carry out major work on such a busy route.


“However, after careful discussion with the train operators and industry partners, it became apparent that carrying out this vital investment over five longer closures between May 2014 and Easter 2015 when fewer people travel would, overall, cause less disruption.”


During the project, the signalling at Watford will be upgraded alongside new junctions and track to provide more flexibility for train services and better reliability.


Patrick Verwer, London Midland managing director, added: “We want our customers to have good journeys with minimum disruption.


“This is much needed investment and a series of closures is the quickest way of bringing the benefits of this major upgrade to our passengers. It gives certainty and allows us to plan good quality alternative travel arrangements.”


Chris Gibb, chief operating officer for Virgin Trains, said: “We shall ensure that all customers have a reliable way of travelling to and from London principally by being able to use other train operators’ services but in some cases by taking a replacement coach service for a short portion of the journey.


“We are starting a dialogue now with industry partners that puts the customer first, but at the same time allows Network Rail to carry out this essential work.”


Network Rail is also investigating the feasibility of increasing line speed of the fast lines through Watford to 125mph from the current 80mph.


opinion@railtechnologymagazine.com TELL US WHAT YOU THINK


rail technology magazine Aug/Sep 13 | 61


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92