The Retrofi t Roofi ng Game: Due Diligence and Existing Building Inspection


By Mark James 10 METAL CONSTRUCTION NEWS June 2012


This month’s topic addresses upfront due diligence on a potential retrofi t project. This subject is very complex and extremely hard to adequately explain in one article. However, there is considerable information available on the Internet. One website you may want to explore is from Bossier City, La.-based McElroy Metal, www.mcelroymetal.com, where you can fi nd a retrofi t design guide to download.


A thorough examination of the existing building and its roof is necessary, both above and below the deck, to know what the effect a new retrofi t will have. Besides geometry modifi cations, you are making some drastic changes to the existing roof. Some considerations will be explained in detail in the coming months, but generally they are as follows:


• The new roof creates a cavity—or an “attic space”—between the old and new roofs. This space must be ventilated to assist in condensation control and to help dissipate any trapped moisture in the existing substrate.


• All of the light-gauge steel framing and metal roofi ng that will be erected on the existing roof will add a considerable amount of weight. The simple fact is the old roof was not originally designed for this additional weight, and you must provide for that in your overall retrofi t design.


• The retrofi t framing must be attached for the existing roof in a way that it will stay on the roof, preventing it from coming off due to wind exposure. I have seen retrofi ts that failed with 70 mph wind speeds, when the code required 90 mph. The key to this is attaching to the existing roof supports (joists).


• In most cases, the retrofi t project will be subject- ed to building code review and approval. This means engineering and installation documents must be prepared and submitted to obtain a building permit.


• The existing roof and its bracing system will receive loads from the new construction. Because of this, the existing building must provide a service- able diaphragm for bracing itself laterally.


• The existing roof assembly, including the deck, insulation and membrane must be inspected for trapped moisture. If moisture is present, the existing roof should be removed entirely or at the


affected areas at a minimum. Premature failure of your retrofi t anchors could result in moisture infi ltration into the building.


• All penetrations through the existing roof during the retrofi t construction must be sealed temporar- ily with a compatible sealant. There is no worse feeling than getting a call from a building owner that his roof is leaking after you have left the job site for the day. Check with your fastener distribu- tor for what sealant should be used based on the type of existing membrane.


• If your retrofi t design requires continuous-type base framing—normally zee-shaped members—it is wise to shim these enough to permit rainwater to drain to the existing drainage system. Other- wise, you may very well dam the water on the roof causing a catastrophic roof failure. Normally a shim thickness of about 1/2-inch will suffi ce.


• The existing roof substrate must be tested to determine its compressive strength. The physical dimensions of the base member at each attach- ment point must accommodate the downward act- ing loads to prevent depressing the substrate. The result, if you don’t do this, can cause a severely undulated roof after the fi rst snowfall long after you have completed the job.


• A structural analysis of the existing roof system should be performed by a qualifi ed engineer using your retrofi t manufacturer’s design documents. This will ensure the roof will not be overloaded. Retrofi t system manufacturers typically do not pro- vide this service. This topic will be discussed next month in more detail.


This month we have only touched on some fun- damentals of retrofi t roof systems. The important thing to remember is you are attempting to change the structural integrity of an existing building roof and, if not conducted properly, the results could be devastating with you holding all of the liability.


Mark James has more than 40 years experience in the retrofi t and metal construction markets, work- ing for leading manufacturers and executing great projects. Currently, he is president of RetroSpec LLC, a consulting company offering direction and deep knowledge of the retrofi t business for manu- facturers and contractors. James can be reached at mark@retrospecllc.com.


www.metalconstructionnews.com


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60