This page contains a Flash digital edition of a book.
CABLES


Clive Woods, programme manager for the Great Eastern OLE renewals project, discusses the vast task of replacing overhead cables with minimum disruption.


T


he Great Eastern overhead line renewals project involves the


replacement of cable equipment that has been in operation since the 1930s. Starting in 2007, this complex programme of works has run from Liverpool Street to Shenfield, and will continue to Chelmsford by the time it is completed in December 2014.


Programme manager Clive Woods spoke to RTM about this comprehensive project, the new and innovative working practices involved, and managing the Olympics em- bargo.


Ageing equipment


He said: “This is very old equipment which is very heavy to work on. Clearly we have some reliability issues. The project is replacing everything along there; most of the structures and all of the overhead lines are being replaced with a Swiss system. It has auto-tension to remove the need for speed restrictions in hot weather.


“At the moment we’ve replaced all the lines that we were remitted to, up to the London side of Stratford station: all of that is complete. We’ve also completed a couple of miles on the country side of Stratford station – some of that is now complete and were just starting work around the Ingatestone area.”


Considering the cables have been in opera- tion for such a long time, it could be as- sumed that technological advances would lead to significant differences in the system. But Woods said: “It’s still the same sort of system that’s been up there since the early days, which is quite surprising when you think about how long it’s been there.”


There is some wear, dependent on the pan- tographs that are being used, but these are inspected on a very regular basis to ensure that any in poor condition are identified and replaced.


Concentrated construction


The project is costing in excess of £200m, with the greatest bulk of work conducted in blockades during Christmas and Easter. Since there is such a small possession


76 | rail technology magazine Feb/Mar 12


window for the work to take place in, this involves deploying around 200-300 people each time – making good management essential.


To make the most of the limited time available to the team, negotiations with the operator have allowed this period of work to be extended to include midweek nights, from Monday to Wednesday. Staff can then put in foundations and structures alongside the track and conduct trial holds and inspections.


Woods said: “Previously on possessions during the night time we’d only get about half an hour to an hour’s working time, which is not very effective. So we agreed with the operator extended times in the evenings. That’s giving us about four to four and a half hours on the track. We’re delivering huge amounts of work during that time, which is significantly reducing the length of time that we’re going to have to work later on.”


Network Rail has also just begun work with the OCR (Overhead Condition Renewals) team, using wiring trains to speed up the process of renewal. These replace the manual practice of de-wiring and re-wiring from baskets on elevated work platforms with a method that is “almost automatic”.


The trains have pre-loaded wire on drums, and the team can then work off platforms built onto the train, wiring onto the machine itself.


“That’s some fairly major new technology that we’re deploying. Previously the length of track that we’ve been wiring would have taken in excess of two years. We’re anticipating being able to do that in basically under a year. That will make a significant reduction in the time the project takes,” Woods commented.


The Olympic embargo


The maintenance organisation has been running inspections leading up to the Olympics; ensuring faults are rectified prior to this event. The cable renewal project will be halted during the Games, resuming in the autumn when both the Olympics and Paralympics are out of the way.


Woods explained: “If you go into an area and try to upgrade it or modify it, you’ve got a risk that the modifications have a chance of failure. If you’ve made a mistake, which we hope we won’t, it’s not worth the risk.


“Leading up to the Olympics there’s a lot of maintenance work being undertaken.


© Network Rail


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92