This page contains a Flash digital edition of a book.
MECHANICAL CONTRACTING Ready to go at 50 below North Pole, Alaska: Men and machinery take on the rigors of winter


near North Pole, Alaska. “Ready to go at 50 below” is their motto, and rightly so. F-16 fighter jets and their crews need to be in top condition, ready to move out at a moment’s notice. So do the mechanical systems on base. Of course, the Alaskan climate


N 64


dishes out an ice-cold punishment all its own. “Our average temperature in January is negative 10, but it dips well below that,” said Al Morlan, superintendent for Slayden Plumbing and Heating, based in North Pole.


“And when the winds kick in, it’s downright brutal, even for locals.” In 2008, Eielson AFB undertook


the construction of 349 new, multiple-family housing units (or multiplexes), and 99 existing units received mechanical system upgrades, all completed by Slayden P+H. Neither the general contracting firm, Fairbanks-based Osborne Construction, nor Slayden P+H, are newcomers to military work. For the past four years, Slayden has installed over 1,000 mechanical systems in facilities nearly identical to the ones at Eielson. They’ve got it down to a science.


Double espresso for Henry Ford Others see it as life in the fast lane,


a caffeine-fueled rush to get a lot of groundwork done between winter seasons. No wonder it seems that there’s a coffee shack on every corner in Alaska, even in some of the most rural spots. Dark coffee and espresso help the locals leap from each deep freeze into the next one, a period of about 120 days. In the North Pole region, there’s a


four-month period when ground can be broken and foundation work safely concreted or poured, including radiant heat work. In late July, dozens of crews at the new housing development at Eielson were moving at an amazing pace to outrun the coming of the next freeze, expected within six or seven weeks. If Henry Ford had invented the


mass production of houses, not Model Ts, he’d have been just as comfortable here, surrounded by


Eielson Air Force Base undertook the construction of 349 new, multiple-family housing units (or multiplexes), and 99 existing units received mechanical system upgrades, all completed by Slayden Plumbing and Heating.


construction teams, each focused on a task they’ve repeated for months with little variation. Within one block, all facets of


construction were underway simultaneously. At the beginning of a cul-de-sac, excavators were moving soil for a poured footer. The concrete truck, spinning slowly, had just arrived. The footer crew was 10 minutes behind schedule.


Modular housing on steroids Next to that foundation was


another one where the footer had cured sufficiently to cover with rigid foam insulation and reinforcement wire. Thirty feet away was another multi-housing unit, its foundation work advanced by exactly 24 hours. Here, a crew was attaching radiant PEX tubing to the re-wire, with taped-shut tubing ends tied to temporary rigging where, perhaps by the very next day, the tubes would be connected to a radiant manifold and attached to the wall of a preassembled, modular mechanical room. A different concrete truck was on its way down the street, bound for this site, ready to pour the slab floor, concealing the tubing. And, next door, now moving into


the curve of the cul-de-sac, a forklift gently placed a small, modular component of the home onto the slab; this six-foot by six-foot, covered section was the mechanical room.


The roof was temporary, but it served its purpose, permitting key mechanical components to be installed in advance. Within a week or two, the rest of the building would rise up beside it. By that time the mechanical team will be a few blocks away, repeating the process. “All the new units need to be under


roof and heated by the first of October,” said Morlan. Quite a task, considering excavation for new housing units on the 500-acre site had only begun in mid-April. Units in every stage of completion,


from excavation to occupation, could be seen from any vantage point on base last summer. Over the past two summers, the military essentially built a town with a population of 1,500 in nine months. Three or four 1,800-sq.-ft. homes make up each well insulated, slab-on-grade multiplex. Each is hydronically heated, with delivery best suited to the Alaskan climate; radiant heat downstairs, fin-tube baseboard upstairs.


District heating makes a comeback We’re on a military base, and a big


one at that. Naturally, they have a few secrets. So when we asked to see the source of all these Btu, we were told that the main steam plant was


e Continued on p 68


icknamed the “Icemen,” the 354th Fighter Wing flies out of Eielson Air Force Base


phc may 2011 www.phcnews.com


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152  |  Page 153  |  Page 154  |  Page 155  |  Page 156  |  Page 157  |  Page 158  |  Page 159  |  Page 160  |  Page 161  |  Page 162  |  Page 163  |  Page 164