search.noResults

search.searching

saml.title
dataCollection.invalidEmail
note.createNoteMessage

search.noResults

search.searching

orderForm.title

orderForm.productCode
orderForm.description
orderForm.quantity
orderForm.itemPrice
orderForm.price
orderForm.totalPrice
orderForm.deliveryDetails.billingAddress
orderForm.deliveryDetails.deliveryAddress
orderForm.noItems
OFFSHORE (PT 1) Ӏ SECTOR SNAPSHOT


three turbines at the port, working in weather conditions where wind speeds can reach 10m/s. Mammoet joined the project in the planning phase, advising on crane selection and logistics for moving components arriving from The Netherlands and For-sur-Mer. To reduce the impact of wind


delays all turbine components were delivered to the port before assembly began. A large lattice boom crawler


crane, a CC8800-1, was used for the main lifts, while two 200t mobile cranes assisted to carry out tailing operations. The heaviest item was the 380t nacelle. The project team reinforced a


40m area of the quay to withstand loads of up to 30t/m, using layers of wooden mats over gravel to


prepare the ground. Mammoet deployed 24 lines of self-propelled modular transporters (SPMTs) to transfer the turbine parts across the port, from the quayside to dedicated laydown areas and onwards for assembly.


A video of the job can be seen here: https://shorturl.at/oTakb


32 CRANES TODAY


Mammoet


transporting a substation for what will be the world’s largest wind farm: Dogger Bank


LIFT AND SHIFT They say ‘necessity is the mother of invention’ and to help make the movement of increasingly large monopiles faster and more cost-effective Mammoet is not just developing new methods it’s creating new hardware, too. At the end of 2025 it publicised a new XXL monopile lifting and transport system comprising an upgraded terminal crane (MTC) that can lift mega monopiles into the water for offshore feedering, and a specialist patented jacking- and-cradle system for their safe handling, using SPMTs.


Mammoet used the equipment


at the port of Ronne, Denmark, where 21 monopiles were offloaded, stored, capped and then lifted into the water. No civil work was needed to reinforce the quay (which would have been required if a crawler crane had been used). The marshalling was for the 315MW Windanker offshore wind farm, which was being fed by Rotterdam, Netherlands-headquartered global marine contractor Van Oord in the German waters of the Baltic Sea.


The monopiles arrived at the


port of Ronne from Spain, the heaviest weighing 2,150 tonnes and measuring approximately 87 metres in length, with a diameter of ten metres.


Fitted with Mammoet’s XXL monopile transport system, 90 axle lines of SPMT lifted them off their grillages and cradled them securely as they were driven off the vessel. They were then taken to a temporary storage location and placed onto sand bunds, ready to be called off for capping to make them watertight. The added stroke of the XXL monopile transport system allowed the monopiles to be lifted higher so that the indents of the storage bunds could be deeper, improving their support while using fewer materials. At the capping location a


LR1750 crawler crane installed plugs onto the top and bottom ends of each monopile. Then the monopiles were driven to the quayside in front of the two MTC1600 cranes, which Mammoet developed specifically to lift XXL monopiles onto vessels and into


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53