PROJECTS


View from adjacent open car park of the building portraying a well proportioned building with facade expression of distinct geometric pattern and colors


KIP CORE SENTRAL


Nestled within the commercial area of the developing Kota Warisan, KIP Core Sentral is divided into two commercial


offices and SoHo units, with car park provided within four levels of podium above the commercial floor.


MATERIALS PROCUREMENT & STORAGE The fact that it was not a high-budget development meant that the choice of building materials was limited. Apart from the glazing and the screens, the façades were mostly done in plaster and paint. Most construction materials and architectural finishes were also locally procured based on the most competitive tender.


Material procurement and storage were properly planned and executed. This is to avoid the negative impacts of shortage or excessive inventory on-site. Deficiencies in the supply and flow of construction materials often lower productivity and lead to financial losses. Ordering small quantities of material in batches could minimise the locked-up capital in material


66


inventories, but it may increase the risk of shortage and project delays. On the other hand, procuring materials in bulk will secure the supply but is also risky in terms of capital tie- up. The project manager considered these critical trade-offs to avoid any logistic problems, cost overruns and delivery delays.


One solution is to identify the optimal ordering period of each material, which changes dynamically according to the fluctuating demand over the project duration. For example, reinforcing steel is usually required in all stages whereas curtain glass walls are required only in the later stages, so the order must be calculated carefully i.e., when, how much and how long the waiting time is.


Aside from this, the procurement must also consider utilisation of spaces on-site to avoid any mishandling and to optimise layout decisions. First, planners have to identify free spaces for material storage areas to calculate the order. Then, they also


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112