THE MAGAZINE FOR THE DRAINAGE, WATER & WASTEWATER INDUSTRIES


TECHNICAL FEATURES


Tony Kitchen


development of the new WIS as part of a multidisciplinary panel which included pipe manufacturers, water company representatives and trade organisations.


Careful consideration was given to onsite implementation of the new requirements, and how contractors can be supported in meeting the standard.


Pressure testing services at AHS are already fully compliant with WIS 4-01- 03 and incorporate the latest technology and real-time assistance from the company’s in-house analyst teams to give contractors unrivalled support throughout the testing process, ensuring that testing is right first-time.


temperature of the pipe to stabilise once it has been filled.


● The allowable air content has now been reduced from 8 to 4 per cent


● The air content must also be accurately calculated during the ‘ramp- up’ stage as the pipeline is brought to system test pressure (STP). This means that the test can be immediately abandoned if it is over the acceptable limit.


What WIS means for contractors


There is no question that the new standard represents a significant step towards leak-free networks, but the new requirements potentially impose a greater burden on contractors. The stringent rules around correct preparation prior to testing, including pre-pressurisation, thermal conditioning, and calculating air content prior to starting the test, making it crucial to get the test right first time, to prevent wasting time and resources in retesting.


A reduction in the allowable air content means less margin for error, which highlights, from a compliance and cost perspective, the importance of contractors carefully managing their


FOLLOW US


own and subcontracted pipeline pressure testing.


Due to the increasing complexity of hydrostatic pressure testing and varying levels of expertise among technicians and operators, some pressure testing providers may not meet the standards outlined in the WIS and could lack the knowledge or skills to correctly prepare the pipe for testing.


Contractors must ensure that all pressure testing activity is fully compliant with the new WIS specifications. Substandard testing potentially creates dangerous situations, with risk to life and limb, if air is not properly removed from the pipeline.


It is crucial for contractors to select subcontractors with proven compliance to ensure the safety and reliability of their projects if they are to maintain both contractual obligations and a good reputation in the industry.


Proven expertise


AHS Pipeline Innovation is recognised as an industry leader in hydrostatic pressure testing with over 20 years of experience and almost 50,000 tests completed. The proven expertise of AHS allowed the company to play a key role in the


AHS is equipped to guide and support teams in adopting these new standards so that their pipeline operations meet the necessary requirements. Should water companies and contractors be unsure about how WIS 4-01-03 affects their operations, or require support to ensure compliance, AHS is available to provide the knowledge and tools necessary to navigate this transition smoothly and effectively.


WIS 4-01-03 not only mandates stricter controls over variables like air content, ambient pressure and temperature, it also effectively identifies and removes any activities undertaken onsite that can affect test performance. Importantly, it reintroduces rules that had been relaxed in previous guidance, restoring rigorous standards that are essential for maintaining the integrity of water systems and creating more defined regulatory expectations.


In addition, pressure tests carried out in accordance with the WIS are measured using sophisticated algorithms that deliver definitive test outcomes, ensuring clarity and reliability.


At a time when the water sector is experiencing reputational challenges, WIS 4-01-03 represents an opportunity for water companies and contractors to get it right from the start. By carefully navigating these changes, and ensuring that every test not only meets but exceeds the latest standards for safety and efficiency, they can mitigate risk to the public and their own teams altogether.


October 2024 | 23


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72