INSTRUMENTATION • ELECTRONICS


Pipeline control stations employ 12 and 16in ball valves automated by Rotork IQ electric actuators. Each valve has a solar panel


Liam Jones details how electric actuators were used in a solar- powered automation project on produced water pipelines


R


ecently, a US water management company requested help to develop solar-powered control stations for some of its water-gathering pipelines


in West Texas and New Mexico. Produced water, a by-product of oil and gas production, is taken from wells and gathered via a pipeline to transfer it to temporary storage at either a disposal well or a central treatment facility.


THE REASON To improve its water-gathering operation, the customer worked with an industrial equipment supplier to investigate automated valve technology to control fl ow in the high-pressure pipelines. T e customer had specifi c requirements


for the valve application, including the need to control system pressure to and from well sites, shut down lines in the event of a leak or other failure, and to eliminate high maintenance devices such as air compressors and other rotating equipment.


THE SOLUTION With a lack of available gas and electricity in the isolated locations, the use of solar power to control pipeline fl ow was regarded as the most eff ective alternative.


62 www.engineerlive.com T e customer wanted valves installed


every fi ve miles in off -the-grid areas, so a solution combining solar panels with control stations and Rotork IQ3 electric actuators was devised. Each control station includes an IQ3 multi-turn actuator to control either a 12 or 16in ball valve and each assembly is fi tted with solar panels to power either a 24, 48 or 120 VDC motor. T e solar power stations off er an


effi cient way of powering the control stations, while also preventing harm to the environment and cutting installation costs by removing the need to install power lines along the length of the pipeline. T e customer provided Rotork with the solar panels and necessary details to correctly size them to the actuators, allowing Rotork Site Services to assemble the systems. Each station was then given its own solar


set to create the power needed to actuate single-stage modulating and isolation valves as well as run a 24 VDC Programmable Logic Controller (PLC). A control panel is also being used to


operate voltage regulators that monitor battery voltage. T e batteries are only charged when the voltage drops below a specifi ed level to prevent degradation by over-charging the battery.


ACTUATORS IN ACTION Rotork engineers were also able to help


test the valves and confi rm they would continue to stroke with no sunlight for at least two days. Due to the presence of complete sunlight on the day of the test, covers were placed over the solar panels. Battery power was used to stroke the valves fully open and closed fi ve times each day during a three- day period.


When the covers were removed, the batteries began charging immediately and reached full capacity in two to three hours.


THE RESULTS T e water management company now has an innovative and safe solution to assist with transporting contaminants to water- gathering and disposal facilities. T e use of Rotork’s intelligent IQ3 actuators in an innovative solar set solution allows the appropriate voltage to safely operate isolation and modulating valves along the pipeline.


Liam Jones is with Rotork. www.rotork.com


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68