RESEARCH & INNOVATION


FEATURE SPONSOR


ENSURING THE SUPPLY OF RENEWABLE ENERGY


Through its investment and engineering capabilities, Balfour Beatty believes it is well positioned to support industry plans to harvest some of the UK’s most remote renewable energy sources.


INDUSTRY CHALLENGE


The UK Government has set targets committing the country to generate 15% of its energy needs from renewable sources by 2020. Offshore wind makes a significant contribution in helping the UK to achieve these objectives and having the necessary infrastructure in place to connect windfarms to the onshore electricity grid is equally critical.


CONNECTING HULL & HUMBER


In 2012, Balfour Beatty was awarded a contract to design, supply, install and commission 30km of 132kV land cable to connect E.ON’s Humber Gateway windfarm (OFTO) to the UK’s electricity network at Hedon substation in Hull. The windfarm is situated 8km off the


East Yorkshire coast and consists of 73 turbines which are capable of generating 219MW of electricity – enough to power around 170,000 homes each year. In September 2016, Balfour Beatty, in consortium with Equitix, was selected by Ofgem to own and operate the offshore transmission link to E.ON’s Humber Gateway windfarm for the next 20 years. Balfour Beatty’s Power Transmission & Distribution business is also responsible for the operation and maintenance of the OFTO’s assets.


EXPERIENCE & DELIVERY


This is the company’s fourth operations and maintenance contract to provide full asset management services on OFTOs. It also marks a step change in contracting philosophy in the OFTO service sector


as they move from a deterministic approach to a probabilistic outputs based approach, challenging contractors to reduce costs through recognising efficiencies ensuring tasks are carried out more efficiently to reduce costs. With a team of specialist engineers and carefully selected strategic supply chain partners in place, Balfour Beatty will manage and operate one onshore and one offshore substation, 18km of subsea cable and 30km of land cable.


SERVICES


They will also deliver a number of services which include: operational control, safety and switching services, routine and reactive maintenance (including first response) and marine services, including personnel access and subsea surveys on both the offshore export cable route and substation platform.


Balfour Beatty


46


www.windenergynetwork.co.uk


HUMBER UPDATE


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116