2 BACKGROUND TO THE PROJECT


2.1 Background to the East Anglia Zone 3.


In 2008 The Crown Estate (TCE) announced the third round of offshore windfarm leasing, ‘Round 3’, with the aim of delivering 25GW (gigawatts) of new generation capacity from offshore wind by 2020. East Anglia Offshore Wind Limited (EAOW) has entered into a Zone Development Agreement (ZDA) with TCE for Zone 5, the East Anglia Zone, located off the coast of East Anglia in the southern North Sea. East Anglia ONE was the first project to be brought forward in this zone. The proposed East Anglia THREE project is the next to be brought forward in the zone. East Anglia THREE Limited (EATL) has been set up by EAOW to develop this project.


2.2 Background to the proposed East Anglia THREE project 4.


2.2.1 Outline Project Design


2.2.1.1 Offshore Components and Activities 5.


It is anticipated that the proposed project will consist of the following offshore infrastructure:


 Offshore wind turbines and associated foundations (anticipated to be up to maximum of 172 wind turbines, each having a rated capacity of between 7MW and 12MW, with an installed capacity of up to 1,200MW);


 Scour protection around foundations and on inter-array, interconnection and export sub-sea cables as required;


 Offshore collector and converter stations with foundations (up to five);  Up to two meteorological masts (met masts) and their associated foundations;


 Sub-sea cables between the wind turbines (inter-array) and the offshore platforms, between offshore platforms and East Anglia ONE (interconnection) between the offshore platforms and the shore (offshore export) and fibre optic cables; and


 A possible separate accommodation platform with associated foundations.


2.2.1.2 Onshore Components and Activities 6.


HRA High Level Screening May 2014


It is anticipated that the proposed project will consist of the following onshore infrastructure:


East Anglia THREE Offshore Windfarm Page 2


The proposed project covers an area of approximately 305km2 and is situated 69km from its closest point to the port of Lowestoft.


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67