This page contains a Flash digital edition of a book.
Impact


Impact 2: Change in Water Quality due to Re-suspension of sediments during construction in the offshore cable corridor (installation of cabling).


Key design parameters forming the realistic worst case scenario Rationale


reality, trenches would be V shaped and therefore less sediment would be disturbed.


The maximum cable installations within the offshore cable corridor includes the installation of up to 620km of HVDC export cable, which would result in the disturbance of up to 31,000,000m3 of sediment (some of which would be released into the water column) by cable installation.


The maximum realistic speed of cable installation is likely to be approximately 450/hr.


Up to four export cables would be installed.


The worst case cable installation techniques would be jetting / vertical injector techniques, which relies on either fluidisation or liquefactions of the sea bed.


The sediment disturbance during cable installation takes a very conservative approach assuming that all cable trenches would measure 5m depth by 10m width as those are the maximum possible dimensions (Chapter 5 Description of the Development). In reality, trenches would be V shaped and therefore less sediment would be disturbed.


Impact 3: Change in water quality due to re-suspension of contaminants within sediment.


As above for Impacts 1 and 2.


The worst case scenario relates to activities that involve the most re- suspension of near surface sediment.


Sub surface sediments have not been exposed to the water column and contaminant sources; therefore, they are likely to contain low levels of contamination. Whereas, near-surface sediments are likely to contain higher concentrations of contaminants due to their exposure to the water column. Therefore, the worst case scenario would involve the installation of gravity base structures.


The rationale relating to sea bed preparation and installation of gravity base structures as well as the cable installation are therefore relevant here.


Impact 4: Change in Water and Sediment Quality due to Accidental Releases or Spills of Construction Materials or Chemicals


It is anticipated that a maximum of 45 vessels would be on site at any time during the construction of the proposed East Anglia THREE project with up to 39 vessels involved in the construction and a further six commissioning components of the windfarm where construction had been completed.


Preliminary Environmental Information May 2014


The greater the number of vessels on site the greater the chance of accidental spillage.


East Anglia THREE Offshore Windfarm


Chapter 8 Marine Water and Sediment Quality Page 6


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44