This page contains a Flash digital edition of a book.
machinery repair VSPs overhauled during one month docking


Gibdock has completed the renewal of two Voith Schneider Propeller (VSP) units on board the 57-tonne bollard pull harbour tug Siroco. The 2001-built 57-tonne bollard pull Boluda


group harbour tug Siroco arrived in Gibraltar in early June for a one-month docking that included the complete removal and overhaul of the two Voith Schneider Propeller (VSP) units on board. As soon as the vessel was drydocked, it was high-pressure jet washed and scraped to remove marine growth. Four plates were then cropped and two upright supports were removed to allow access for Gibdock engineers to remove the VSP blades. John Taylor, Gibdock production director, said: “This was a time consuming task and it took around two shifts to remove all 10 blades and transport them to the workshop for overhaul. This included disassembling, cleaning, calibrating and remounting the bearing assembly with new spare parts and all the blades had to be inspected and polished.”


Odessos Shiprepair Yard in Varna, Bulgaria, has completed a technically complex machinery overhaul on the ex-Lauritzen- owned Lapponian Reefer. Work consisted of dismantling, refitting and machining a new- generation hydraulically operated propeller hub and controllable pitch (CP) propeller tail shaft. The shaft was 8600mm in length and weighed 12,600kg. The hub weight was 10,600kg. The CP propeller had a diameter of 5,600mm and the weight of the blades was 10,800kg.


The vessel involved was a modern reefer vessel managed by Holy House Shipping of Sweden, a longstanding customer of Odessos. The scope of the work consisted of overhauling the CP propeller hub, and overhauling and renewing bearings and bushing. Work included:


Gibdock engineers then removed the two


rotor casings and transported them to the workshop. The main cover plate nuts were removed using a hydraulic torque multiplier, and all internal components, including pistons, gears, actuating rams and the thrust shaft were similarly transported to Gibdock’s mechanical workshop for overhaul. The VSPs’ rotor casings were then lowered from the vessel and, with the assistance of the yard’s shore cranes, were lifted from the dock bottom and transported to the workshop. Once the Voith Schneider units and rotor casings had been removed, the main deck fixtures were completely protected and the two openings were blanked off before blasting. Following the dismantling and inspection of


the rotor casing, the bearing flange assembly and protective ring was found to be extremely corroded. It was decided to fabricate and fit steel inserts to the two bearing flange assemblies. “Although this was unexpected extra work,


Next generation CP propeller hub repaired


• machining crank discs’ seats to new bearings size • guide bearing of cross-head, modification by machining and renewal of bronze liners • cross-head – machining the grooves and modification • crank discs – four pieces, machine and polish including pins • new sliding blocks – fabrication • fabrication of bearing crank discs, radial and axial (four sets x three pieces) • preliminary workshop tests of the complete system and pneumatic functional testing. Specialised workshop mechanical procedures were completed in 10 days, employing six to eight different machines simultaneously, in daily shifts, with an additional day for pre- assembly and pneumatic tests.


we incorporated a night shift to complete the repairs as soon as possible, in order not to affect the undocking date, which was crucial to the owners,” said Mr Taylor. The new inserts were machined to an external diameter of 1,285mm, internal diameter of 1,065mm and a 60mm thickness. These inserts were then fitted to the existing bearing flange assembly. While in the workshop, all the mechanical parts of the VSP units were cleaned and calibrated and the data recorded, and all the seals, packing and bushes were renewed, with Gibdock engineers working closely with service specialists from Voith Turbo Schneider. The reassembly of the VSP units in the workshop continued while a second full coat of paint was applied to the hull. Once the Voith Schneider systems were completely reassembled onboard and the access plates refitted and welded, a final full topcoat of silicone paint was applied to the tug’s hull and the vessel left for sea trials.


Other work on engine room machinery included extensive fuel oil tank cleaning and surveys, piping in the engine room, specific piping and connections renewed by stainless steel pipes, fitting ballast lines, pneumatic activation system of valves, a major overhaul of the Tenfjord steering gear, and testing of the 2, 000kW shaft generator. Work was also carried out on the cargo gear cranes, with the 36-ton crane jibs removed ashore for repair, renewals and modification of the pins and bushing at the jibs’ base, including functional and load tests.


Despite the unforeseen repairs to the bearing flange assemblies, the vessel was completed to the dry docking schedule of 30 days. No problems were encountered during the sea trials and the tug is now back in operation in Algeciras. MP


Inspecting a propeller hub cross-head www.mpropulsion.com


Close up of the hydraulically operated propeller hub Marine Propulsion I February/March 2012 I 91


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132