This page contains a Flash digital edition of a book.
In this regular section, we look at cases of poor-quality workmanship, mistakes in installation and shoddy practices. John Rothwell from ELECSA provides an insight on what can go wrong – and how best to avoid it


The installation:


This was a total refurbishment of a cottage, including a full re- wire of the electrical installation. At the time of the inspection, fi rst fi xing was in progress, and provision had been made for the use of 230V power tools by the installation of temporary BS1361socket outlets. The type of supply system was via an overhead line, and necessitated the use of a consumer’s earth electrode to provide a return path for fault


current so that protection could be effectively provided. This is the earthing system that the BS7671:2008 wiring regulations defi ne as ‘TT earthing’.


Several trades were involved in the refurbishment


work, each requiring power for electrical power tools, such as drills, saws and so on. As working conditions can be onerous in this type of environment, and therefore the measures used to protect the users of electrical equipment under these conditions are particularly stringent, it is always the focus of the inspection to ensure that the protective measures afforded and that those used to prevent electric shock are adequate.


About the author


John Rothwell John Rothwell IEngMIET is a senior inspector in ELECSA’s inspections team and has been working in the electrical industry for 42 years.


What went wrong: It was established that the 230V socket outlet provision was not afforded 30mA RCD protection. It was also ascertained by testing that the earth loop impedance was infi nitely high and, as such, the protective devices affording overcurrent protection would not provide protection against fault current in these circumstances. On further investigation, it was discovered that the earthing conductor originated at an earth electrode comprising of a metallic tube driven into ground at the front elevation of the property. The earthing conductor was disconnected at the earth electrode, which accounted for the infi nitely high earth loop impedance value obtained in the test previously described.


64 ECA Today March 2011


The outcome: Fortunately, the failure to provide adequate safety measures to prevent electric shock did not result in injury or fatality. It is likely that the contractor would have had to have defended themeselves against a charge of negligence had serious injury or death occurred.


What should have been done? Construction sites are particularly diffi cult work environments, where hazards are sometimes compounded, for example, by the presence of water and use of heavy plant and equipment. Section 704 of BS7671:2008, entitled ‘Construction and Demolition Sites’, outlines specifi c safety measures in these environments. The requirements for supplies for socket outlets and other circuits supplying hand- held equipment up to and including 32A rating are that they should be protected by one of the following measures: (i) Reduced low voltage; (ii) Automatic disconnection of supply with ‘additional protection’ provided by RCD(s) rated at not more than 30mA and tripping within a time not greater than 40mS when tested at fi ve times the rated residual current;


(iii) Electrical separation, with the isolating transformer supplying only one item of electrical equipment; or


(iv) Separated extra-low voltage (SELV) or protective extra-low voltage (PELV).


While measures (i) and (ii) are those commonly


used, it should be pointed out that Section 704 strongly recommends that portable hand lamps for general use and portable hand tools and local lighting up to 2kW should be supplied by reduced low voltage.


This could have been avoided by: Verifying that the earthing of the incoming supply was effective prior to starting the work, and also ensuring that 30mA RCD protection was afforded at the main intake. In this case, the work necessitated the installation of a proprietary earth electrode (as, in our opinion, that in situ was not suitable) within an inspection pit complying with


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72