Oil hazards


As a result, early fire detection in conjunction with additional measures to improve fire protection infrastructure is now a key element of damage limitation. In turn, the tank farm operating company, in


collaboration with the FRS, can now effectively respond to possible fire scenarios – even in the case of power outage or if access to the tank farm is blocked by a cargo train, as shown in the model scenarios in Figures 1 and 2. By implementing the alternative fire protection concept, the tank farm operator was able to ensure the required safety objectives were achieved and an equivalent level of safety provided. The three packages of measures were able


to compensate for the shortcomings of the fire protection infrastructure. In comparison to the previous concept proposed by the engineering firm, the TÜV SÜD solution saved the tank farm operating company roughly one third of the originally estimated costs of rehabilitation


Michael Daub is a preventive fire protection expert and project manager for fire protection


Scenario 1:


Parameters: Time until arrival of fire brigade around 15 minutes, free access to tank farm II, power supply undamaged


FOCUS


Detection of a change of temperature in one tank


Reporting to control centre, staffed 24/7


Remote activation of tank cooling by sprinkling


Cooling insufficient, Fighting of incipient fire with foam extinguisher system


Reporting to integrated fire control centre


Fighting of incipient fire


Figure 1: Example scenario 1 of incipient firefighting: intact power supply and free access to the tank farm (Source: TÜV SÜD).


planning and rehabilitation at TÜV SÜD Industrie Service GmbH, and Torsten Welz is project manager for early fire detection systems at DIAS Infrared GmbH. For more information, view page 5


Scenario 2: Parameters: Time until arrival of fire brigade around 15 minutes, access to tank farm II blocked; approach for fire-fighters from road, power supply broken down


Power loss Power supply, monitoring and


alerting of fire-detection system by means of battery buffering


Detection of a change in temperature in one tank


Reporting to control centre, staffed 24/7


Activation of emergency power unit (diesel generator)


Remote activation of tank cooling by sprinkling


Cooling insufficient, Fighting of incipient fire with foam extinguisher system


Reporting to integrated fire control centre


Fighting of incipient fires


as far as possible due to position of cargo train


Figure 2: Example scenario 2 of incipient firefighting: power failure and blocked access to tank farm by freight train (Source: TÜV SÜD).


www.frmjournal.com OCTOBER 2019 31


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60