EDITOR’S CHOICE


Why off-site manufacturing is gaining ground in Irish construction


By Eugene Sheehy, Associate, Will Rudd Ireland T


he conversation around modern methods of construction (MMC) in Ireland is often framed around the need


to build faster. The programme is undoubtedly important,


particularly in housing, but our experience across residential and infrastructure projects suggests the more interesting question is where off-site manufacturing can genuinely improve the way a project is designed and delivered. Ireland has a well-established tradition of


masonry construction, supported by a mature supply chain and experienced workforce. Timber frame, precast concrete and other prefabricated systems offer different advantages, with their value shaped by the building type, scale and conditions in which a project is being delivered. Will Rudd is working with Waterford City and County Council on a 38-unit housing development in Dungarvan, where we developed the civil and structural design and tender documentation for Design & Build procurement. The development combines several


construction methods. Timber frame is being used for 22 terraced houses, while 16 apartments use loadbearing masonry walls with precast concrete first-floor slabs and stairs. Prefabricated timber roof trusses feature across all units. This hybrid approach allows the structural solution to respond to each building type. Timber-frame panels can be manufactured while foundations and other site works progress,


allowing activities to overlap before the superstructure is erected. Factory manufacture provides a controlled


environment for production and quality assurance, with potential benefits for waste, labour, logistics and safety.


It also places greater emphasis on early coordination. More of the architectural, structural and services design must be resolved before manufacture, allowing potential issues to be addressed before components reach site. Will Rudd is also advising on an 80-unit residential development in Kilkenny, comprising terraced houses, duplexes and apartments. Procured through Design & Build, the scheme allows contractors to put forward compliant structural systems rather than prescribing one construction method. At this scale, repetition across building types creates greater scope for off-site manufacturing. Standardised components can be produced in a controlled factory environment while work continues on site, offering potential gains in programme certainty, quality control, efficiency and waste reduction. Any proposed system still has to perform against cost, durability, fire and energy performance, embodied carbon and supply-chain capacity. The construction method also has to make sense for the development as a whole. www.willrudd.com


14 September/October 2026 Irish Manufacturing www.irish-manufacturing.com


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48