www.heatingandventilating.net


Combined heat & power


CHP meets school’s heat and power demands sustainably


Mark Gibbons, CHP national sales manager at Baxi Commercial Solutions, looks at how a combined heat and power (CHP) system is efficiently reducing energy bills and improving comfort levels in a historic boarding school


F


or UK organisations looking to set their buildings on the path to Net Zero, the journey will be less straightforward for some than


others. Improving the way older, harder-to-heat historic buildings, like Aldenham School in Elstree, are heated can be particularly challenging. Aldenham, which dates back to 1597, offers both


Boarding and Day options for girls and boys on its expansive historic estate. When the ageing boilers serving one of its


boarding houses, Paull’s House, reached end of life, the forward-looking School was keen to explore solutions other than replacement to improve its green credentials. Alongside this goal, the requirements were to ensure an efficient heating and hot water service for the boarders, connect the system to the neighbouring science block, and complete the work within the summer shutdown period. Reliability was also key as neither Paull’s House nor the science block could be without hot water.


Complex retrofit issues in the draughty 16th Century building meant that the school had already had to rule out use of renewable heating technologies. “We were working with an extremely old building in which parts of the fabric date back to the 16th century,” explains Tony Albon, the school’s head of estates. “So, we decided to call in the heat experts for advice.” A successful partnership was built with heating manufacturers Baxi Commercial Solutions. Tony and Karl Mahon, Aldenham’s Bursar, held lengthy discussions with the Baxi Commercial Solutions team who carried out multiple site visits to understand the exact requirements before presenting the feasible options. “It was clear that the most viable solution to meet


all our needs was a combined heat and power (CHP) and condensing boiler system,” Mr Albon continues. “Not only can this solution meet the space heating and large domestic hot water requirements more efficiently at Paull’s House, reducing energy demand, but it produces electricity at lower costs for use within the building.” CHP produces useful heat and electricity at the point of use in a single, highly efficient process. Rather than rejecting ‘waste’ heat to atmosphere like traditional power stations, CHP captures it and feeds it into the building’s heating network to produce useful thermal energy. This energy can then be used to provide primary space heating and/or pre-heat for domestic hot


Mark Gibbons, CHP national sales manager at Baxi Commercial Solutions


water within the building. By simultaneously generating heat and onsite power, the system can typically achieve a total fuel efficiency of 85- 90%, double that of conventional technology. That means primary energy savings of up to 30% and an emissions reduction of around 20%, compared with traditional generation. “The Baxi team really took the time to explain the


proposed solution,” said Tony. “They also arranged visits to sites where similar Baxi CHP systems had been installed. It was great to be able to see the CHP in situ, hear the building owners’ own experiences and come away with an accurate, realistic idea of the energy saving benefits.” After completing a feasibility survey and a final assessment of the heating and hot water demand at Paull’s House, a Remeha R-Gen SenerTec Dachs G5.5 CHP was selected, supported by three Potterton Commercial Sirius three 110kW wall hung condensing boilers. The project contractors were Keeble Environment Services. Both the CHP unit and the ultra-low NOx stainless-steel boilers are compatible with the proposed introduction of 20% hydrogen into the


gas network, enhancing the sustainability of the installation. “The collaboration has resulted in the best possible solution for the School, meeting all our objectives,” Tony added. “The CHP team has been by our side throughout the project. They also brought in their technical, training and commissioning experts to support us and the contractor.” Baxi’s specialist team will be carrying out all future maintenance and servicing as well as providing training to ensure that the CHP continues to deliver as designed. “Our boarding students have commented on the


improved comfort levels in Paull’s House, as have the teachers in the science block,” Tony continued. “Sustainability was an added driver, and we anticipate an annual reduction in electricity costs of around £3,500 and a saving of over 6,000 kg of carbon from the CHP. It’s a fantastic result – we have great plans for further projects with this partnership.”


DOWNLOAD THE HVR APP NOW September 2022 33


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44