search.noResults

search.searching

dataCollection.invalidEmail
note.createNoteMessage

search.noResults

search.searching

orderForm.title

orderForm.productCode
orderForm.description
orderForm.quantity
orderForm.itemPrice
orderForm.price
orderForm.totalPrice
orderForm.deliveryDetails.billingAddress
orderForm.deliveryDetails.deliveryAddress
orderForm.noItems
BSEE


The Danubius Hotel Regents Park in London made an investment to modernise their boiler plant, upgrading their aging boilers that had reached the end of their life cycle. Contractor SPIE UK and Hamworthy Heang delivered a spacesaving soluon with Hamworthy’s Wessex ModuMax mk3 boilers to provide heang and hot water without interrupon for the busy hotel


ocated by Lord’s Cricket Ground, Regents Park and the renowned Wellington Hospital in central London, the Danubius Hotel is a popular destination for travellers and business people alike. With 360 bedrooms/suites and a fitness centre, a reliable heating and hot water supply is crucial. Prior to the refurbishment, this was provided by 14 cast iron atmospheric boilers with a total output of 3,850kW. However, faulty components and other issues indicated the end of their life. The plant room consisted of the following: 14 cast iron boilers split into two banks of seven boilers with individual shunt pumps; separate primary circulating pump (which was grossly undersized for the system); AHU circulating pumps; fan coil unit circulating pumps; two split 500mm single skin flues with an N+1 bifurcated fan; pressurisation unit with undersized expansion vessels; and eight 750 litre indirect hot water calorifiers with plate heat exchangers on an open vented system.


L Challenges of a busy hotel


While the hotel had to be kept running 24/7 during the change, constant incoming travellers from local airports put extra pressure on, making down time impossible. SPIE had to find a compact boiler with high maximum working pressure and heat output to accommodate the heating and hot water supply to the eleven floors of hotel rooms. Together with Hamworthy’s sales manager for the area, Noel Lally, four Hamworthy Wessex ModuMax mk3 WM254/762V boilers with a combined output of 3,048kW including pipe header kits and a remote signal kit were identified as the ideal solution. This model consists of three boiler modules stacked on top of each other and can operate at a working pressure of up to 10 bar which was needed to match the height of the building. At the core sits a stainless steel heat exchanger that comes with a 10-year warranty. A small footprint of 0.74m2


per boiler stack


makes it easy to transport and site in narrow plant rooms.


uFour Hamworthy Wessex ModuMax mk3 boilers with three modules each deliver a total output of 3,048kW to the hotel


SPIE’s senior project manager, comments: “We chose the Wessex ModuMax mk3 boilers due to their slim profile and the 10 bar working pressure. It’s also efficient, streamline, compact and easy to use. The alternative, a competitor product, only had a safe working pressure of six bar. I chose the pipe header because they’re a simple piece of kit with a plug and play installation. When the boilers are all lined up and within a couple of hours the headers bolted to them, it sure does


look impressive to your clients. Easy to install, just nuts and bolts and a level. “For the controls, I chose the interface kit to give the boilers full rotation via the building management system to ensure even use across the equipment. It also allows full modular control to suit the system characteristics, meaning the boilers will match the load and operate as efficiently as possible.”


Updating the flue system


A change from atmospheric to condensing boilers meant the flue system needed to be reviewed. Firstly, the stainless steel liner up to the roof, approximately 40 metres, was removed. With the use of CCTV, the SPIE team inspected the concrete fabricated existing flue. The challenging flue installation was overcome by utilising FuranFlex composite liners in the existing chimney stacks to deal with the condensate and pressure of the new boilers. After applying the flue liner, they cut a spigot into the wall to be upgraded to 600mm up to the flue dilution fans from which it was reduced to 500mm to the main stack.


The project manager, adds: “We used an N+1 configuration on the flue dilution fan system with differential pressure switch piped across the fan chamber so that in the event of a failure, we had a backup and automatic changeover would occur.”


Separating old from new


The contract that SPIE signed with the building owners was based on zero complaint strategy, which meant absolutely no complaints to avoid damaging costs. Originally, the pipework and valves were intended to be reused. But due to failing valves letting by and an uninterrupted stream of hotel guests, SPIE UK’s senior project manager decided to install a whole new 12-metre-long 400mm low loss header and interconnect the Wessex ModuMax mk3 boilers to maintain a primary heat source. Then slowly (at low peak) demand, cut the pipes to each separate circulating system, and integrate to the low loss header. This meant new power supplies, isolators, variable frequency drives (VFDs) and pipe work needed to be ready for the cut in. This was done to avoid disruption to the existing heating circuits. To accommodate this process, existing pipework was frozen by Industrial Piping Freezing Services (IPS), pipes cut and new flanges welded in by IPS and new isolation valves/regulating cut in. The work was extensive. The existing main plant room housed the main boiler plant and calorifiers, and there was a small plant room that accommodated all ten circulating pumps. Installing the new low loss header and relocating the main primary circulating pumps down with the boilers meant it was an ideal opportunity to relocate all ten circulating pumps down where the old atmospheric boilers once used to sit. This also included the installation of new isolating valves, circulating pumps, expansion vessels, a pressurisation unit and a side stream filtration unit. On the controls side, a whole new building management system was installed by Electrocom Projects.


The project manager comments: “The main benefit of starting from


scratch was that it allowed us to install a new system (primary) to the boilers and then start interfacing this with the old pipework, effectively creating a hydraulically separated system and ‘re-energising’ the existing one. This is why we needed the boilers earlier than anticipated. The entire project, during which we converted the heating system from open-vented to closed took us nine weeks from the start to completion.”


Wrapping up


The existing heating system was successfully upgraded while the challenge to keep the hotel running without interruption to accommodate guests was successfully met. To suit the needs of a high-rise building and restricted space, Hamworthy’s Wessex ModuMax mk3 boilers, benefitting from a high working pressure and a small footprint, were chosen.


The project manager concludes: Since the installation, we have noticed massive improvements in gas consumption. Where the boilers before always seemed to be at 50 per cent or 100 per cent, the noticeable turndown on the Wessex ModuMax boilers is amazing. After finishing the installation, we chose Hamworthy to commission our boilers because it extends the warranty and keeps it clean – I wouldn’t have it any other way. “Their team is very knowledgeable about their own products and commission thoroughly. I have worked with Hamworthy for nearly 10 years across projects and have a good relationship with the sales managers. We always receive excellent support and service, before and after sales.”


www.hamworthy-heating.com 10 BUILDING SERVICES & ENVIRONMENTAL ENGINEER AUGUST 2019 Read the latest at: www.bsee.co.uk


uThe Danubius Hotel was under constant pressure due to an uninterrupted stream of visitors during the refurbishment


FOCUS: HOTEL & LEISURE Heating under pressure at the Danubius Hotel





Given the


setup, a careful planning process was crucial to ensure a smooth transion to the new system





Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58