| HRSGs and boilers HRSG market shares: McCoy reports


John Cockerill reports that it achieved number 2 position in terms of MWe market share for heat recovery steam generators in 2023 according to McCoy Power Reports. John Cockerill recorded a MWe market share of 19.9% as HRSG technology owner (OEM, including licensees). Mitsubishi was in the number 1 slot, with


an estimated MWe market share in 2023 of 31.6%, helped by its Chinese licensee Dongfang Boilers.


At positions 3, 4 and 5 in terms of 2023 MWe market share were, respectively, Nooter Eriksen (13.8% market share), GE Vernova (12.5%) and NEM Energy (7.6%).


In terms of market share by number of heat recovery steam generator units, the 2023 top five was: Mitsubishi Power and Nooter Eriksen (both 16.5%, 17 units); Vogt Power International (11.7%, 12 units); John Cockerill (10.7%, 11 units); Kawasaki Heavy Industries (9.7%, 10 units).


John Cockerill: recent awards


Among recent HRSG-related orders reported by John Cockerill was that placed by Luminus (EDF subsidiary) for detailed engineering, procurement, manufacturing, and construction of two diverters to be installed at the 470 MWe Seraing unit 1 combined cycle plant in Belgium, very much on Cockerill’s home turf.


To be placed upstream of the heat recovery steam generators designed and supplied by John Cockerill in 1993, the divertewrs will convert the plant to open cycle and render it better able to operate as a peaker, running when electricity demand is high.


John Cockerill says it “proposed a unique, smart and competitive solution, which will result in a huge benefit for Luminus. The electricity producer will be able to use the existing gas turbines in open cycle with higher power output…and with quicker start-up times and adapt more efficiently to peak electricity demand.”


One of the challenges posed by the project will be to organise the work in an extremely restricted area, requiring “rigorous sequencing of tasks to fulfill stringent safety rules.” Another recent award to John Cockerill was by Siemens Energy for the design and supply of a horizontal exhaust flow Benson-type HRSG (3 pressure & reheat) to be installed behind a Siemens Energy SGT5-4000F turbine in the Adamov combined cycle power station in Poland, located some 200 km west of Warsaw.


Owned by ZE PAK SA (Zespol Elektrowni Patnow Adamow Konin), this new 600 MW power plant, being constructed by a consortium of Siemens Energy and Mytilineos. It will replace a five-unit coal-fired power plant built between 1964 and 1966 next to the Adamow brown coal mine and now decommissioned.


The new power station will contribute to the energy transition in Poland, which still relies on coal for around 70% of its electricity production, by far the highest proportion in the EU, with the government having recently adopted ambitious targets for moving to lower-emissions power.


NEM Energy in Uzbekistan and Brazil NEM Energy is to supply a DrumPlusTM heat


recovery steam generator, including exhaust gas bypass system, for the 520 MWe Jizzakh combined cycle power plant in Uzbekistan. The power plant is expected to be in operation by the end of 2025.


NEM signed the contract directly with end- customer and operator Cengiz Enerji of Turkey. The HRSG, using second-generation DrumPlus


technology, will have excellent fast start and cycling capabilities.


NEM and Cengiz see “a great deal of future potential” arising from this project. Meanwhile, in Brazil, under a contract signed with Global Participações em Energia S.A. (GPE), NEM Energy is supplying two vertical-exhaust-flow drum type heat recovery steam generators, also including exhaust gas


bypass systems, for a new 165 MWe combined cycle power plant in Manaus, Brazil. It is similarly expected to be in operation by the end of 2025.


NEM Energy points out that it has “many units in successful operation in Brazil as well as in other countries in Latin America” and these have provide “reliable references” in obtaining the new contract.


www.modernpowersystems.com | April 2024 |23


John Cockerill horizontal exhaust flow Benson-type HRSG


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43