search.noResults

search.searching

saml.title
dataCollection.invalidEmail
note.createNoteMessage

search.noResults

search.searching

orderForm.title

orderForm.productCode
orderForm.description
orderForm.quantity
orderForm.itemPrice
orderForm.price
orderForm.totalPrice
orderForm.deliveryDetails.billingAddress
orderForm.deliveryDetails.deliveryAddress
orderForm.noItems
21ST-CENTURY DESIGN


keen to push this further. There were significant constraints in the ground, typically for a previously developed site, which we felt could be tackled more efficiently using 3D design technology. We started by modelling key parts of the existing drainage. There was an existing foul drain that ran at about a 5 m depth diagonally across the site and served other parts of the hospital, so could not be abandoned; its depth was such that it was impractical to divert it. Using survey information, we were able to model this pipe in 3D, and include it in the structural model, which simplified the process of modelling and coordinating the foundations around it. We really, however (excuse the unintended pun) broke new ground with two other challenges presented to us – the routing of a new fibre optic cable, and an underground service trench routed through an area congested with existing drainage.


Fibre optic cable


The existing telecoms cable ran across our site close to the fracture clinic which the new therapies building was going to abut. The RUH masterplan required the cable to be renewed before construction work started on Therapies, but this presented a significant construction risk. An alternative route was found around the new building, which gave rise to another challenge – because this area was fairly congested with services and tree root protection zones. To compound matters, the hospital needed to include new surface water drainage and HV cable diversions within this enabling package. This package of work was to be carried out by a different contractor, and within a tight timescale. Accurate, detailed information had to be given to the contractor to allow it to rapidly understand and execute the project. It was essential that the coordination happened in the design office, rather than on site.


Detailed modelling


While not the usual role of a civil and structural engineer, the RUH asked for our assistance in a coordinating role. We modelled each existing pipe and cable with its actual diameter, plan position and depth, taken from the topographical and buried services surveys. New services information was provided by the associated specialists, and root protection zones were added to the plans. No special or additional information was needed. Where we were getting near to the new Therapies Building, we referenced in our model, and even modelled the boundary walls, to assist in party wall matters. Manholes were modelled to the correct size and depth and setting out. It was even possible to model trenches to see


102 Health Estate Journal October 2019 Doyouwant to be‘virtually enabled’?


In pushing the boundaries of 3D technology and modelling we have learned several valuable lessons in order to maximise efficiency and value: n It is essential for all designers to use the same 3D modelling software, including contractors, such as the MEP sub-contractor, for seamless coordination.


n The coordinating role is becoming more distributed across disciplines now, and is no longer purely the preserve of the architect.


n Design meetings can be focused around the 3D model on the screen, which enables a real-time interactive approach to stakeholder engagement. This works particularly well when assessing accessibility for CDM.


n A 3D model is far easier to understand for people not familiar with construction drawings, and thus gives a real impetus for early engagement, as well as preventing costly redesign later in the design process.


n Projects can be built ‘virtually’ before starting on site, which reduces the risk of programme delays and cost uncertainty.


Daniel Barnett, of the RUH Estates Capital Projects Team, said: “3D modelling was highly effective in co-ordinating the enabling works. It gave reassurance that existing constraints in the ground and future building elements – including a service trench – had been considered, which allowed the civils contractor to sequence the works safely on a busy hospital site. The BT duct diversion was a critical item which – if not done correctly – would have had a major operational impact on the A&E Department and wider hospital. Fundamentally, 3D modelling helps us carry out due diligence and reduce operational risk.”


The dispensing robot in place.


The dispensing robot in action.


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152  |  Page 153  |  Page 154  |  Page 155  |  Page 156  |  Page 157  |  Page 158  |  Page 159  |  Page 160