search.noResults

search.searching

saml.title
dataCollection.invalidEmail
note.createNoteMessage

search.noResults

search.searching

orderForm.title

orderForm.productCode
orderForm.description
orderForm.quantity
orderForm.itemPrice
orderForm.price
orderForm.totalPrice
orderForm.deliveryDetails.billingAddress
orderForm.deliveryDetails.deliveryAddress
orderForm.noItems
OFFSITE CONSTRUCTION


constant improvement of internal logistics, such as flow of materials and waste, and processes for improving lead times.


A healthcare example of a temporary offsite facility One of the first examples of ‘offsite’ construction in hospitals in the US was led by the architecture firm, NBBJ. The main driver for prefabrication in this case was not simply to prove that a building could be manufactured, but rather the aesthetic and functional aspects of the project that required a high level of personalisation for a particular healthcare client. This first project in which prefabrication was implemented by NBBJ was undertaken at the Cardiac Center of the Miami Valley Hospital in Dayton, Ohio, a 12-floor, 480,000 ft2


building with a construction


cost of US$ 137 million (Andía and Spiegelhalter, 2015).6


Once the hospital design was


completed, NBBJ and contractor, Skanska, determined which elements could be modularised, and five prefabrication


MEP frames


All the MEP frames that go over the circulation corridors were manufactured in


initiatives were defined: unified external curtain walling; a temporary pedestrian walkway; the manufacture of nurses’ workstations; the creation of patient rooms through the prefabrication of walls and bathrooms (Fig. 1), and an integrated rack system which houses all mechanical, electrical and plumbing infrastructure above the corridors.


Initiatives 3, 4, and 5 listed above were the most innovative. For these, Skanska leased a warehouse approximately 5 km from the construction site, and prefabricated the components offsite. All the modular bathrooms and the walls that made up the patients’ rooms were built in the warehouse. The installation of the modular bathrooms and the walls was able to be undertaken rapidly (Fig. 2). It took an 8-hour day to install 33 bathroom modules, and just one and a half weeks to install 30,000 ft2


of inpatient floor.


the same warehouse facility. All HVAC ducts, control boxes, gas, plumbing, sprinkler lines, electrical conduits, and cable trays, were placed inside 210 MEP prefabricated racks. The 8 x 22 ft MEP racks fit over the 16 ft wide corridors of the hospital wings. It took a day to transport and deliver a full floor of racks, and between and one and one and half weeks to secure the racks in their final position.


NBBJ Architects says the work undertaken in the prefabricated warehouse was ‘more productive’, with just 18 staff prefabricating the 180 patient rooms and the 210 MEP racks over a three-month timescale. The architect and the builder observed that there was a great improvement in the quality of construction, a reduction in construction errors, and improvements in both productivity and job security. They also noted a faster schedule and a significant reduction in construction waste. A good example of the productivity gains achieved was in the installation of


Figure 6: Views of the BLOX manufacturing plant.


August 2019 Health Estate Journal 25


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69