This page contains a Flash digital edition of a book.
not be known until sometime after the DCO has been granted. However, the installation methods and rates presently being considered are described in Table 7.9.


Table 7.9 Cable Installation Methods and Rates Technique Ploughing


Description


Cutting through the sea bed with a blade, behind which the cable is laid


Trenching or cutting Jetting


Excavating a trench whilst temporarily placing the excavated sediment adjacent to the trench and back-filling the trench once the cable has been laid


Fluidising the sea bed using a combination of high-flow low pressure and low-flow high pressure water jets, enabling the cable to sink beneath the sediment surface


Vertical injector


Using a large jetting or cutting share strapped to the side of a barge for cable laying at the foot of a trench in shallow waters


66.


Installation Rate 150-300m/hour


30-80m/hour 150-450m/hour


30-80m/hour


Of the above cable installation techniques, jetting is considered the worst case in terms of this assessment since it results in greatest suspension of sediment off the sea bed and into the water column.


67.


For purposes of the EIA, a worst case assumption has been made that some form of cable protection measures would be required at cable crossings and in areas where cable cannot be buried (e.g. areas of exposed bedrock).


68.


Alternative cable protection measures presently being considered include concrete mattresses, fronded concrete mattresses, rock dumping, bridging or positioning of gravel bags.


69.


For the inter-array cables, the worst case is that there would be up to 10 cable crossings and that up to 10% of the inter-array cables would be unburied and require protection. The total footprint area of cable protection measures would range from 0 to 720m2. The height of cable protection measures from the sea bed would range from 1 to 3m.


70.


For the export cables, there would be a number of cable crossings required. These would particularly be in the area where the East Anglia THREE offshore cable corridor crosses the export cables of the Greater Gabbard Offshore Wind Farm and Galloper Wind Farms.


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm Chapter 7 Marine Geology, Oceanography and Physical Processes Page 15


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95