Bisham Consulting has helped River Island develop a new European Distribution Centre Complex with a high level of resilience to ensure it will accommodate activities planned for at least the next five years.


Future proof W


ith over 60 years of fashion retailing


experience, River Island is one of the most successful retailers on


the High Street and its continued success will be supported by its brand new European Distribution Centre located in Magna Park, Milton Keynes. The 45,400m2


building’s graduated


blue-grey tinted cladding blends its 15m height smartly into the sky though it is actually two separate units interlinked by twin bridges, a solution that gives this retailer the capacity and resilience it needs – vital issues for any retailer.


River Island’s continued growth was leading inevitably to space constraints in the retailer’s two existing DCs located in nearby Tongwell – as well as its separate e-commerce fulfilment site. In 2007 the retailer decided to look carefully at its next 10 years of forecasts.


“At that stage we needed somebody to evaluate from a scientific point of view, what we believed we needed to meet these forecasts,” said Arif Ahmed,


logistics director of River Island. Having considered several consultancy companies, River Island awarded Bisham Consulting the contract to help develop a strategy to address several key issues.


European expansion The most prominent was that the retailer’s primary DC was built to initially serve around 110 stores yet it now has some 300 stores. Moreover, growth was continuing as River Island was expanding into Europe via franchises and own stores. Risk management around business continuity is another vital issue for River Island, which delivers to all of its stores from the DC including those in Europe. In an environment as competitive as retail, having the ability to ensure business continuity, even under catastrophic circumstance, is crucial. One of the first things Bisham Consulting did for River Island was to carry out a review of its existing DCs. This indicated that process improvement benefits alone, would not be large enough to accommodate


River Island's growth projections. Then, working together, the partners devised a new future-proofed European Distribution Centre to replace these facilities yet give the retailer plenty of room for expansion together with complete flexibility to help mitigate risk in its business. Bisham Consulting identified the levels of future proofing required based on River Island’s requirements that would accommodate future peaks, which in retail can account for up to 40% of


www.PressOnShD.com October 2011 ShD 27


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76