TECHNICAL | MINED TUNNELING


Right, figure 9:


Underpinned TTC Subway Box. The pink color of the steel truss was part of a breast cancer awareness fundraiser


IMAGE COURTESY OF METROLINX


Optical monitoring targets were installed in the


gallery sidewalls, six in total within each gallery. The red trigger level was 8mm inward displacement. The readings in all the targets indicated a stable condition during the entire gallery construction period with maximum recorded displacements in the range of 2mm. Additional to the in-tunnel monitoring, the entire


TTC tunnel, including the rail tracks, were monitored in real-time. Inside the tunnel, electric level beams and tiltmeters were installed. Additionally, the contractor installed Building Monitoring Points (BMPs) outside the TTC tunnel box to monitor the exterior walls/roof of the TTC box. The differential settlement readings of the rail tracks


within the relevant monitoring tunnel box units (underpinning zone) ranged between 0mm and 2mm throughout the construction of the galleries. The alert


level of 3mm was breached twice on one single instrument inside the TTC subway tunnel but the reading was discarded as a false reading due to temperature fluctuation. No action response by TTC and the contractor was required.


CONCLUSIONS A novel underpinning solution of the operational TTC Eglinton West station for the construction of ECLRT Cedarvale station was undertaken utilizing a series of small, mined galleries. These galleries provided access to install a supporting system of steel (needle) beams. The main challenges were the confined space and the tight differential displacement criteria of the TTC box. The construction of the mined galleries was completed in just over two months. The impact of the works on the operational subway was negligible.


Right, figure 10:


Grouting preparation and finalized grout bags


18 | Winter 2023


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57