search.noResults

search.searching

saml.title
dataCollection.invalidEmail
note.createNoteMessage

search.noResults

search.searching

orderForm.title

orderForm.productCode
orderForm.description
orderForm.quantity
orderForm.itemPrice
orderForm.price
orderForm.totalPrice
orderForm.deliveryDetails.billingAddress
orderForm.deliveryDetails.deliveryAddress
orderForm.noItems
TECHNICAL | MINED TUNNELING


Temporary decking (schematic)


Eglington Avenue West Existing TTC Spadina box TTC box joint Unit 1604


gallery C


SEM L


elevation varies Springline


Extended gallery 1A


Gallery 1A


Gallery 3


Gallery 2


Gallery 4


Gallery 1B


gallery C


SEM L


gallery C


SEM L


TTC box joint


Unit 1608


gallery C


SEM L


gallery C


SEM L


gallery C


SEM L


TTC box joint TTC box joint Unit 1612


Needle beam (indicative) Bracing not shown for clarity


Springline elevation varies


Temporary vertical prop


Existing TTC spadina box


Temporary vertical props Bracing not shown for clarity


T/R


CL


CL T/R 1300mm caisson


SEM gallery springline


Approx. 10110 Above, figure 3: Combined plan view and transverse section of the completed galleries under the TTC box


Dewatering of the permeable soil layers was


implemented using deep wells prior to underground excavation in order to lower the groundwater level and to control groundwater inflow, mainly as part of the subsequent, main station excavation works. The geotechnical properties used in the design are summarized in Table 1.


UNDERPINNING SYSTEM The underpinning system consisted of a series of needle beams transverse to the alignment, installed through the six mined galleries. The two ends of the needle beams were supported during construction on temporary steel girders founded on caissons, and in the permanent configuration were connected to reinforced concrete wall-beams integral to the station structure. A jacking system provided the means to adjust the elevation of the needle beams and compensate for potential excessive movements, based on the real-time monitoring of the TTC box. Six mined galleries were constructed in total, as


shown in Figure 3, supported by a continuous lining of fibre reinforced shotcrete (FRS) at the sides, structurally connected to the invert slab. Each of the six galleries was divided longitudinally into eleven advances,


14 | Winter 2023


typically 1.1m-long, excavated simultaneously from both sides. Galleries 1A, 1B, and 2 which were excavated first,


were 4m-wide by 2.75m-high, U-shaped with a cross section as shown in Figure 4. The walls were supported by a 100m-thick shotcrete lining, following a concave shape, increasing to 300mm at the top connections to the TTC box. A first, 100mm-thick shotcrete layer was applied immediately against the sides of the exposed ground concurrently with the full thickness of the invert, whereas the completed profile of the sides was applied in a subsequent step. The invert slab was FRS, 350mm- thick, cast-in-place. Gallery ‘1A Extended’ was essentially an enlargement


of Gallery 1A with a concurrent removal of its left-side wall and shares the same geometrical characteriztics. Only its left side was supported by the full shotcrete lining whereas the invert slab is similar to the other galleries. Galleries 3 and 4 were excavated between the


completed Galleries 1A, 1B and 2, and they did not require side support. A 50mm-thick shotcrete layer (flashcrete) was


sprayed against the exposed excavation faces in all galleries.


SOUTH SIDE


NORTH SIDE


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57