TECHNICAL | MINED TUNNELING


TTC box walls


top/bottom slabs


TTC box


Underpinning mined galleries


Bottom slab/soil interface


Above, figure 5: Simulation of the existing TTC box and the completed underpinning galleries


Challenges during Construction


Several challenges encountered during the execution of the works are described in the following sections.


Confined Working Space The biggest challenge in this project was working in confined space under the existing TTC subway box. The contractor faced a very tight environment caused by existing support elements, the steel waler beam, and the subway box itself. This became more challenging once the first needle beams within the galleries had been installed. The prompt and uneventful execution of the works required a skilled construction team equipped with the smallest available plant.


Grout Bags Grout bags were placed between the vertical props and the TTC box to ensure a full connection (see Figure 10).


The grout bags were installed with vertical props and precast concrete pad footings with their connecting beams before applying the first shotcrete layer. With changing weather conditions and colder ambient air temperature setting in, the grout curing time increased significantly.


TTC Box Slab / Mud Slab During the excavation of Gallery 1B an unexpected amount of previously poured concrete underneath the TTC box base slab was encountered, which was not documented in the as-built drawings. This additional concrete appeared also in other galleries and resulted in a significant amount of extra time and work effort. Chipping of the concrete was only permitted by hand


(jackhammer) as directed by TTC. No excavator or similar heavy equipment was allowed due to working beneath the live operating subway.


Total displacement min (stage): 0.000m


max (stage): 0.044m


0.0000 0.0005 0.0010 0.0015 0.0020 0.0025 0.0030 0.0035 0.0040 0.0045


Above, figure 6: 2D FEA galleries Results: Total Displacements 16 | Winter 2023


Joint


Joint


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57