search.noResults

search.searching

saml.title
dataCollection.invalidEmail
note.createNoteMessage

search.noResults

search.searching

orderForm.title

orderForm.productCode
orderForm.description
orderForm.quantity
orderForm.itemPrice
orderForm.price
orderForm.totalPrice
orderForm.deliveryDetails.billingAddress
orderForm.deliveryDetails.deliveryAddress
orderForm.noItems
TECHNICAL | MINED TUNNELING


UNDERPINNING OF A SUBWAY AIDED BY MINED GALLERIES


Mined galleries were excavated below groundwater level to help underpin an operational subway box structure during construction of the new Eglinton Crosstown LRT in Toronto. The novel solution is discussed by Dr Angelos Gakis and Thomas Schwind of Dr Sauer & Partners, in Salzburg, and Elmar Feil and Gerald Skalla of Dr G Sauer & Partners, Canada


INTRODUCTION


Cedarvale station was built as part of the new Eglinton Crosstown LRT in Toronto, at the intersection with the Yonge-University (Spadina) line under the existing Toronto Transit Commission (TTC) boxed tunnel of the Eglinton West Station. The new station, an open-cut excavation, required an underpinning of the operational TTC box to ensure an unhindered service. A novel solution was implemented to provide access


to install a series of ‘needle beams’, utilizing six small, mined galleries. The galleries were supported by a temporary shotcrete lining on their sides and a concrete slab at their invert. Rebar dowels were placed at the connection of the shotcrete lining to the overlying TTC box base slab. Additionally, temporary support was provided during the excavation of the galleries by a series of steel props, supported on precast concrete pads, mechanically connected to the invert slabs. All the excavations extended below the groundwater


level. Dewatering was undertaken prior to the excavation of the galleries to lower the groundwater level to below


their invert level and to control groundwater ingress and surface water flow during excavation. The TTC box and the new Cedarvale station as well


as the main underpinning elements are shown in Figure 1. The multidisciplinary design team on the works


consisted of Dr. G. Sauer & Partners (mined elements), Entuitive (structural), and Isherwood (support of excavation). The prime contractor of Cedarvale station was Crosslinx Transit Solutions Constructors (CTSC), a construction consortium of SNC Lavalin Inc., ACS- Dragados, Aecon Infrastructure, and EllisDon Civil. Sub-contractor for the mining works was HC Matcon Inc. (HCM).


EXISTING STATION The existing TTC box is formed of reinforced concrete units, 12.2m-long, 10m-wide and 5.7m-high. The top and bottom slabs and the external walls are approximately 600mm-thick and the inner wall is approximately 460mm-thick.


TTC box joint Unit 1604 Unit 1608


Existing TTC spadina box


Unit 1612 T/R Shotcrete Needle beams T/R


Lowered water table


Underpinning caissons


Underpinning girders


Above, figure 1: Existing TTC box, new station, and main underpinning elements 12 | Winter 2023


SOUTH SIDE


NORTH SIDE


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57