is assembled and glazed onsite, offers the slimmest and most consistent sightlines once installed – typically 50 mm for both the mullion and transom. It also easily caters for staggered transom and mullion options if required.


When I deliver CPDs on the topic of curtain walling, I advise that having a complete curtain wall facade with as few interfaces as possible is the best route to optimising the water and air tightness, and avoiding the inevitable interface issues between trades or differing systems. I also advise specifiers on how to optimise the system for structural performance, taking into account the factors, which can affect the choice of mullion or transom used. This covers whether the curtain walling is fixed inboard or outboard of the slab, the size of cell required, the wind load, and what the predicted building movement will be. Whether the mullions sit in front of or between the slabs though, structural movements and differential deflections in multi-floor buildings can be largely accommodated by the use of either lateral (slotted holes) or dead load (round holes) in the bracketry. For the more slender glass sizes, a major consideration is ‘racking’. This can be particularly problematic if the dead load of the whole system is not directly transferred to the ground. Any slab deflection and the consequential differential mullion movement must be assessed for racking.


Other factors to take into account in a curtain walling specification are the mullion and transom spans (‘lx’ value), the glass types and weights (‘ly’ value) and the glass pane centres, because all will have an


ADF FEBRUARY 2019


effect on the required performance of the finished facade. Without early exploration, the original design intent may need to be compromised to accommodate the issues above. Drainage is always a key consideration as well of course. These days, most curtain walling systems are mullion drained rather than zone drained, with the transoms effectively acting as ‘gutters’ moving any water to the ‘downpipe’ mullions for it to drain through. Increasingly, curtain walling is required to interface with other facade treatments such as cladding and brise soleil. It is essential to consider the strength of the curtain wall mullion nosing, because external items are generally fixed to that through the face of the system, but it is perfectly possible to attach solar shading, walkways, double skin facades and signage. And of course, any product specified must comply with the curtain walling product standard BS EN 1380 and have been tested to the CWCT requirements for air permeability, water tightness and wind load resistance.


Even if you get the specification spot on though, the eventual success of a curtain-walling project can largely be down to the choice of sub-contractor. In awarding the contract, consideration must be given to both cost and capability. Awarding a small project to a large, over resourced sub-contractor can prove just as problematic as awarding a large project to a sub-contractor who is too small to handle it.


Jon Sheaf is major projects manager at AluK


WWW.ARCHITECTSDATAFILE.CO.UK


Increasingly, curtain walling is required to interface with other facade treatments such as cladding and brise soleil


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36