programming of particular works as set out in the indicative programme to be provided under sub-paragraph (b)(iv); and


(viii) any exclusion zones/micrositing requirements identified in any mitigation scheme pursuant to condition 11(j);


to ensure conformity with the description of Works No. 2 and 3A and compliance with conditions 1 to 5;


(b) a construction and monitoring programme to include details of— (i) the proposed construction start date;


(ii) proposed timings for mobilisation of plant, delivery of materials and installation works;


(iii) proposed pre-construction surveys, baseline report format and content, construction monitoring, post-construction monitoring and related reporting in accordance with conditions 11(h), 17, 18 and 19; and


(iv) an indicative written construction programme for all offshore substations and cables comprised in the works at paragraph 2(2) of Part 1 (licensed marine activities) of this Schedule (insofar as not shown in paragraph (ii));


with details pursuant to paragraph (iii) to be submitted to the MMO at least six months prior to the first survey unless otherwise agreed in writing with the MMO;


(c) a construction method statement in accordance with the construction methods assessed in the environmental statement and including details of—


(i) drilling methods and disposal of drill arisings and material extracted during seabed preparation for foundation works and cable sandwave preparation works;


(ii) soft start procedures with specified duration periods;


(iii) offshore substation location and installation, including scour protection; (iv) cable installation, including cable landfall and cable protection; (v) contractors;


(vi) vessels and vessels transit corridors; and (vii) associated and ancillary works;


(d) a project environmental management and monitoring plan to include details of—


(i) a marine pollution contingency plan to address the risks, methods and procedures to deal with any spills and collision incidents during construction and operation of the authorised scheme in relation to all activities carried out;


(ii) a chemical risk assessment to include information regarding how and when chemicals are to be used, stored and transported in accordance with recognised best practice guidance;


(iii) waste management and disposal arrangements;


(iv) the appointment and responsibilities of a fisheries liaison officer and an environmental liaison officer; and


(v) a fisheries liaison and coexistence plan to ensure relevant fishing fleets are notified of commencement of licensed activities pursuant to condition 6 and to address the interaction of the licensed activities with fishing activities;


(e) a scour protection management and cable armouring plan providing details of the need, type, sources, quantity and installation methods for scour protection;


(f) only when driven or part-driven pile foundations are proposed to be used as part of the foundation installation, a marine mammal mitigation protocol in line with JNCC guidelines for minimising acoustic disturbance to marine mammals;


(g) a cable specification and installation plan, to include—


123


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131