This page contains a Flash digital edition of a book.
decommissioning phases would put the safety risks within acceptable limits. These issues are considered further within Chapter 15 Shipping and Navigation.


265. Potential allision risks between windfarm infrastructure and construction / decommissioning vessels and fishing vessels are discussed in Chapter 15 Shipping and Navigation.


14.6.1.4 Impact 4: Increased Steaming Times to Fishing Grounds 266. The implementation of temporary transitory safety zones and advisory exclusion zones during the construction and decommissioning phase could, in theory, result in some short term increases in steaming distances and times, and therefore higher operational costs for fishing vessels. As with safety issues for fishing vessels, the standard environmental impact assessment matrix is not wholly appropriate for considering increased steaming times.


267. In the case of local vessels, which for the most part concentrate their activity within the 12nm limit, and therefore do not venture beyond the proposed East Anglia THREE project, there should be no material adverse impacts on increased steaming times.


268. As shown by Figure 14.12- Figure 14.16 and Figure 14.30- Figure 14.31, the locations of the main fishing ports relative to the majority of fishing grounds for the Dutch and Belgian fleets are such that traditional steaming routes would not involve passages through the area to be occupied by the proposed East Anglia THREE project.


269. Similarly, the majority of the fishing grounds of the Danish, French, Norwegian and German fishing vessels, relative to the location of their base ports would generally not involve steaming routes that would pass through the proposed East Anglia THREE project.


270. During the construction phase, the theoretical worst case scenario for commercial fishing would be the implementation of a 500m safety zone around the entire perimeter of the East Anglia THREE site for the total duration of the construction phase of 30 months (see Table 14.2).


271. In practice however, temporary transitory safety zones can only be placed around foundations and installations that are under construction, the size and location of safety zones changing as construction progresses.


272. In summary, it is not expected that the construction phase of the proposed East Anglia THREE project will have any discernible impact of fishing vessels' steaming


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 14 Commercial Fisheries Page 91


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147