This page contains a Flash digital edition of a book.
the arena containing post-tensioning girders on several levels due to long spans, transfer conditions, and the significant load and deflection requirements in certain areas.A one-way beam-and- slab system was used in the parking structure, which is attached to the arena. Various parts of the project—the parking garage, the arena


and the loading docks—used post-tensioning for different but distinct reasons. In the case of the parking garage, the underground facility


has some special circumstances. RogerWade, a Structural Engi- neer with Qk4, said post-tensioning was used because the owner wanted a long-span structure to accommodate two parking bays and a drive aisle between columns. Also, it was necessary to keep the depth on the parking


garage as shallow as possible. The site is two blocks from the Ohio River; consequently, the water table is very high. The low- est part of the garage is near the normal water table. Having the shallowest structure possible reduced costs, and helped avoid damp conditions. An advantage of using post-tensioned concrete on the garage


was increasing the speed of construction. Using precast would have involved loading and unloading slabs from the city streets. Post-tensioned slabs can be done on-site, and as one slab is fin- ished, it is easy to move on to the next. Other advantages includ- ed the reduction inmaterial by using shallowdepthmembers and decreased cracking. “The arena didn’t need post-tensioning for its typical floor


structure, but it was necessary to have a column-free area to accommodate a practice court,” said Bart Miller, P.E., Senior Associate withWalter P.Moore, structural engineer. (The prac-


tice court is located below the arena seating and runs parallel to themain court.) Additionally, the facility features a curved window wall that


required floors to cantilever up to 17 feet from the structural frame to reach the back of the glass. The structure was designed using stringent deflection limits around the curved window to prevent the concrete from transferring loads to steel supporting the window. Also, two escalators outside the arena yet still within the


building lobby rise 50 feet and apply a 10-ton load to the end of the supporting structure,which cantilevers 16 feet fromthe arena structural frame – all of which was coordinated with Otis. Although chosen primarily for design-build reasons, post-


tensioning has had side benefits. “We saved concrete and we saved formwork,” saidMike Clay, Principal with Populous, the architect. “We really used post-tensioning froma structural stand- point for our spans, deflections and loads. Everything else is an additional advantage.” The projectwas started in late 2008 and is scheduled to open


in late 2010. Other members of the design and construction team, in


addition to Amsysco, Populous, Walter P. Moore and Qk4, include ClasSickle Inc. (associate structural engineer) M.A. Mortenson Co. (construction manager) and F.A.Wilhelm Con- struction (general contractor).


Kimberly Kayler can be reached at kkayler@constructivecommunication.com.


PT


Affinity Partner E


very day your customers depend on you. Tey leave their cars in your parking garage or with your valet and assume everything will be fine. But things can go wrong. Vehicles


disappear from parking garages. Valets crash cars. Pedestrians trip on potholes. And customers file claims. So who can you depend on? For more than


25 years, Alliant Insurance Services has been offering complete insurance solutions for all types of parking operations.We can help you prevent and manage risks while making sure you have the most appropriate coverage for your business. Contact us today.


Customers depend on you.Who can you depend on? Alliant, the specialty insurance leader.


(866) 805-7275, Ext. 775


www.alliantinsurance.com/parking kphillips@alliantinsurance.com


SEPTEMBER 2009 • PARKING TODAY • www.parkingtoday.com 51


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64